POWER GENERATION

PROJECT

SUPPLY OF A REFURBISHED 100 MW RATED PULVERISED COAL FIRED ELECTRICITY GENERATING STATION

TECHNICAL SECTION 03-11-2005

T A B L E O F C O N T E N T

Annexure A Scope of Supply Annexure B Coal Specification

Annexure C Plant Details

Double-Casing Condensing Turbine Three-phase Synchronous Generator Electrostatic Precipitator Conveyor System Cooling Water System

Additional Technical Particulars

ANNEXURE A

SCOPE OF SUPPLY

ANNEXURE A SCOPE OF SUPPLY

POWER GENERATION PROJECT

A - BOILER PLANT

Main Boiler and Boiler House Steel Columns Main Boiler and Boiler House Steel Beams Roof Trusses, Purlins and Girts Roof and Side sheeting including purlins and girts Platforms & Stairs Flooring / Grating

Steam Drum and Support Slings / Hardware Down Comers Boiler Feed Pumps with Cast-In Frames and Base plates including motor - 2 sets Finned Tube Economizer Elements and Headers including Bypass Economizer Gas Bypass Primary Superheater Elements Secondary SH Elements Primary SH Inlet Header Secondary SH / Main Steam Outlet Header HP Steam lines complete with spring supports Boiler Feed lines complete with supports De-aerator HP Valves Feeder Tubes Riser Tubes

ID Fans with Drives ID Fan Ducting ID Fan Dampers FD Fans with Drives FD Fan Ducting FD Fan Dampers PA Fans with Drives PA Fan Ducting PA Fan Dampers

Coal conveyors with Drives and new Belting Coal Storage Bunkers in Boiler house Coal Chutes to Coal Feeders and Mills / Pulverizers Coal Feeders Coal Mills / Pulverizers with Gearbox and Drives Combined Coal / Oil Burners including feed systems and new Wind boxes Hanger Supports for Combustion Chamber Access Doors New Thermal Insulation and Cladding for Boiler, Ducting and Piping Rotary Airheaters with Ducting Soot Blower Supports and Access Platforms and Stairs Electrostatic Precipitator - 5 Field Ash Hoppers with Ash removal system

Structural Steel Design and Foundation Design Boiler Performance Design Pressure parts design review and Inspection Authority for Boiler Certification (TUV) Boiler O & M Manuals Marking of all components for Erection works AUTOCAD and original Drawing package

Dismantling, refurbishment and packing of all components

Delivery of Equipment to any Seaport required for Project.

B - TURBINE GENERATOR SET - SCOPE OF SUPPLY - AEG - 3000 rpm / 50 Hz

HP and LP Top and Bottom Casings complete HP and LP Rotors Condenser complete with Auxiliary Equipment and Cooling Water Pumps Cooling Water System Oil system Generator Transformer Feed Water Heating Station complete with Piping and Valves Turbine Building including Roof Trusses, Purlins, Girts and OH Crane beams Performance Review Turbine Generator O & M Manuals Marking of all components for Erection works AUTOCAD and original Drawing package Dismantling, refurbishment and packing of all components Delivery FOB South African Port.

C - SUPPLY OF NEW ADDITIONAL EQUIPMENT

New Membrane walled combustion Chamber with new Buckstays New Lagging and Cladding New airheater packs Boiler Furnace cleaning Equipment such as Sootblowers

ANNEXURE B

COAL SPECIFICATION

ANNEXURE B COAL SPECIFICATION AT PRESENT LOCATION

The fuel shall be an unwashed product having an as used gross calorific value, quality and grading, approximately, as follows (at present location):

Calorific value 10, 380 B.t.u./1b.
Surface moisture 4.0 % (max.)
Total moisture 6.6 %
Volatile matter 18.0 % normal minimum
Ash 18.0 % (maximum)
Sulphur 1.3 % (average)
Grindability 56 Hardgrove index.

Ash Fusion

Initial deformation temperature 1325°C Softening temperature of ash 1350°C Fusion temperature of ash 1380-1400°C

Sizing

Coal at the mills will be 100% below 1" cube. The grading can be adjusted within limits to give the best operating results.

ANNEXURE C

TECHNICAL DETAILS

DOUBLE-CASING CONDENSING TURBINE

Type 11/100 220

AEG-TELEFUNKEN

1.1 TECHNICAL PARTICULARS

General Rated Turbine Data and Limit Values Oil Supply System Governing Equipment Seal Steam and Drain Equipment Auxiliary and Safety Equipment Metering Equipment Rated Data of Condensing Plant Motor List Weights of Some Heavy Components

TECHNICAL PARTICULARS

General

Type of Turbine 11/100 220

AEG Impulse Type

Double-casing Condensing Turbine

Unit 3 Unit 4 Unit 5

Year of Manufacture 1966 1966 1967
H.P. Rotor Number T 1073 T 1074 T 1121
L.P. Rotor Number T 1085 T 1086 T 1122

Rated Turbine Data

Output, economical 80,000 kW max. 100,000 kW

Live steam pressure, normal 1200 psig (84.4 atg) max. cont. 1250 psig (87.9 atg) max. short-time 1380 psig (97 atg)

Live steam temperature, normal 950 °F (510 °C) Max. cont. 970 °F (521 °C) Max. short-time 986 °F (530 °C) Max. short-time 1009°F (543 °C)

1) 1380 psig (97 atg) are permissible for a maximum of 12 hours per year.

2) The max. short-time live steam temperature of 986 °F (530 °C) is permissible for a maximum of 400 hours per year and

3) 1009 °F (543 °C) are permissible for a maximum of 80 hours per year with the duration of an operation limited to 15 minutes at one time.

Pressure and temperature in stage 1 At 80 MW, 1200 psig (84.4 atg), 950 °F (510 °C) normal 839 psia 873 °F (59 ata) (467 °C)
max. 1132 psia (79.6 ata)

941 °F (505 °C)

The pressure in stage 1 should not exceed 1132 psia (79.6 ata)

Steam flow at 80 MW, Casing I (H.P.) 642,920 lbs/h (291.6 t/h) 1200 psig (84.4 atg), 950 °F (510 °C) Casing II (L.P.) 527,560 lbs/h (239.3 t/h)

Max. steam flow Casing I (H.P.) 821,640 lbs/h (372.7 t/h) Casing II (L.P.) 736,740 lbs/h (334.2 t/h)

No-load steam flow (generator excited) approx. 20,720 lbs/h (9.4 t/h) Condenser pressure norm. 1.82 in. Hg (0.063 ata) max. 3.51 in. Hg (0.1213 ata) Condensate flow norm. 477,740 lbs/h (216.7 t/h) max. 667,120 lbs/h (302.6 t/h)

C.W.
temperature norm. 75 °F (24 °C) max. 90 °F (32 °C)
C.W.
flow 40,330 imp. gal/min (11,000 m3/h)

THREE-PHASE SYNCHRONOUS GENERATOR

WITH HYDROGEN COOLING

Type FKWS 3742 p

AEG - TELEFUNKEN

CONTENTS

1. TECHNICAL PARTICULARS

General Rated Data Electrical Data Mechanical Data Cooler Data Gas and Oil supply System Auxiliary, Measuring and Safety Equipment Control Room Equipment Tables Curve Sheets Oil specification

1.1. General

Generator type FKWS 3742p

Year of Manufacture Unit 3 : 1966 Unit 4 : 1966 Unit 5 : 1967

Stator Nos. Unit 3 : G 8133 Unit 4 : G 8134 Unit 5 : G 8152

Rotor Nos. Unit 3 : I 8133 Unit 4 : I 8134 Unit 5 : I 8152

Main exciter Type ECT 84/31/8 Unit 3 : No. 704 384 Unit 4 : No. 704 385 Unit 5 : No. 710 468

Amplidyne Type GQC 4546sp1 Unit 3 : No. 338 990 402 Unit 4 : No. 338 990 401 Unit 5 : No. 344 426 501

Base exciter Type 245 sond. Unit 3 : No. 705 805 Unit 4 : No. 705 806 Unit 5 : No. 710 454

Gear unit Type DSF 20 x Unit 3 : 5671 Unit 4 : 5672 Unit 5 : 5779

Voltage regulator Type TSA 2

Field rheostat R 250

Hydrogen cooler Type V 15 x 9 – 3021/2 KF 30 203 No. T 850 429

1.2 Rated Data

1.2.1 Rated Generator Data Apparent power 111.1 MVA Power factor 0.9 Active power 100 MW H2 pressure 30 psig (2.11 atg) Voltage 10.5 kV +/- 5% Speed 3000 rev/min Current 6.11 kA Frequency 50 c/s Further outputs can be determined from the power chart.

1.2.2 Rated Main Exciter Data Output 620 kW Voltage 310 V Speed 1500 rev/min Current 2000 A

1.2.3 Rated Amplidyne Data
Output 7.6 kW Voltage 230 V
Speed 1500 rev/min Current 33 A
1.2.4 Rated Base Exciter Data
Output 0.09 kW D.C. 0.7 kVA A.C. Voltage 60 V D.C. 225 V A.C.
Speed 1500 rev/min Current 1.5 A D.C. 3.1 A A.C

The generators are designed in conformity with BS 2613 and should be operated according to these specifications.

1.3. Electrical Data

1.3.1 Resistances at 20 °C

1.1.1 Stator No. 8133

Phase U1 X1 0.00240 ohm Phase U2 X2 0.00238 ohm Phase V1 Y1 0.00236 ohm Phase V2 Y2 0.00237 ohm Phase W1 Z1 0.00239 ohm Phase W2 Z2 0.00237 ohm

1.1.2 Stator No. 8134

Phase U1 X1 0.00241 ohm Phase U2 X2 0.00239 ohm Phase V1 Y1 0.00237 ohm Phase V2 Y2 0.00237 ohm Phase W1 Z1 0.00239 ohm Phase W2 Z2 0.00240 ohm

1.1.3 Stator No. 8152

Phase U1 X1 0.00239 ohm Phase U2 X2 0.00238 ohm Phase V1 Y1 0.00236 ohm Phase V2 Y2 0.00238 ohm Phase W1 Z1 0.00238 ohm Phase W2 Z2 0.00239 ohm

1.1.4 Field winding, slip ring to slip ring

Rotor No. 8133 0.119 ohm Rotor No. 8134 0.118 ohm Rotor No. 8152 0.118 ohm

1.1.5 Main exciter

No. 704 384 Field winding IK 5.02 ohm Compoles GH 0.00098 ohm

No. 704 385 NO. 710 468 Amplidyne No. 338 990 402 Field winding IK Compoles GH Field winding IK Compoles GH Main field ia – ka Control field ib – kb Diff. Field ic – kc 4.98 0.001 5.25 0.00107 28.1 ohm13.2 ohm43.0 ohm ohm ohm ohmohm
No. 338 990 401 Main field Control field Diff. Field ia – ka ib – kb ic – kc 28 13.15 43.1 ohmohmohm
No. 344 426 501 Main field Control field Diff. Field ia – ka ib – kb ic – kc 28.6 13.45 44 ohmohmohm
1.1.6 Base exciter
No. 705 805 No. 705 806 No. 710 454 Field winding CD Field winding CD Field winding CD 16.9 16.9 16.9 ohm ohm ohm
1.3.2 Field Currents
For Maximum output at 30 psig H2 pressure For maximum output at 16 psig H2 pressure For maximum output at 2.5 psig H2 pressure For maximum output at air operation approx. 1700 A approx. 1540 A approx. 1280 A approx. 1040 A

The field currents are no criterion of the load-carrying capacity of the generator.

ELECTROSTATIC PRECIPITATOR

1. GENERAL

Each boiler will be provided with electrostatic precipitator plant to fit within the space available. The precipitator plant associated with each of the boilers shall comprise one independent shell. The precipitator shall be located in the gas circuit immediately ahead of the induced draught fans.

The precipitator shall be situated outside the boiler house and shall be of weatherproof construction suitable for out-of-doors operation in climatic conditions prevailing at site.

The precipitator shall be complete with all electrical equipment. All collector and discharge electrodes, support frames and insulators, rapping gear, motors, dust hoppers, ducting and casings, thermal insulation and other equipment shall be provided.

All access ports and manholes, galleries and stairways, guttering with all necessary rainwater goods and all ancillaries shall be supplied to make a complete working plant.

The H.V. equipment shall be mounted on the roof of the precipitator, and each transformer/rectifier unit shall be equipped with a drip tray and drain piping leading to a common point on the precipitator floor below each casing.

The design and construction of the precipitator shell shall be such as to ensure that air infiltration is reduced to the minimum amount possible.

A special series of access holes with fittings shall be provided by the precipitator contractor at suitable points in the ducting of each precipitator to enable the inlet and outlet dust burden to be measured.

2. DESIGN

2.1 BASE DESIGN

The precipitator shall have plan dimensions not exceeding 25 m x 12 m and shall have a dust collecting efficiency of not less than 99,6 %.

The performance of the precipitators with one electrical field out of service shall exceed 99,1%. This field may take the form of one complete field over the width of the precipitator, or may be two electrically independent half-sections, making up one total field.

The precipitators shall be capable of handling the flue gas quantity as given in Schedule C1 when the boiler is operating under maximum load. It should be noted that the coal is expected to have an average Sulphur content of 2,0 % and that the average sodium content of the fly ash is 0,6 %.

The design of the induced draught fans serving each boiler is based on the following precipitator performance, which must not be exceeded:

(a)
Temperature drop through precipitator at 100% boiler MCR: 6°C.
(b)
Pressure drop through precipitator, the inlet and outlet ducts within the precipitator extent of supply, the gas flow straightening and distribution devices and the inlet and outlet losses at 100% boiler MCR: 500 Pa.

Each precipitator shall be subdivided (in direction of the gas flow) into the number of equally sized fields as is required to satisfy the specified collecting efficiency requirement, but the number of fields shall not be less than five. Each field shall be subdivided (in direction perpendicular to the gas flow) into two independent sections and each section shall be energized by an independent H.V. supply.

Adequate insulation shall be provided between attachments of different metals in order to prevent electrolytic action.

2.2. CASINGS AND SUPPORT STRUCTURE

The precipitator casings shall be of welded steel plate construction in accordance with Standard Building Regulations, Chapter 6 – Structural Steelwork as amended and shall comprise all work, including support columns above ground level and dust hoppers.

The casings shall be capable of withstanding a maximum suction of 5 kpa without distortion or distress. The maximum possible dust load on the precipitator internals shall be taken into account in the design of the casing and the support structure, similarly the load of accumulated dust in the inlet and outlet hoods and flues.

The casings shall be arranged to allow a smooth gas flow with no dead pockets or areas where dust may stagnate and cool.

The precipitator support structure shall be of steel construction.

Access shall be provided from the operating floor of the boiler house to the roof or each precipitator.

No welding shall be carried out on steel set in concrete where there is any possibility of the heat of welding being communicated to the concrete.

All columns, walls, floors and roofs shall be of adequate design and construction thickness and strength to ensure gas tightness, to prevent buckling and distortion, and to withstand loads that may reasonably be expected.

The steel casing shall be designed and stiffened to resist the specified loading. The plates used for the construction of the casing shall have a minimum thickness of 6,0mm.

The casing including hoppers, etc., must be carefully and suitably lagged with approved material, protected on the outside by sheeting similar to that used for flues and ducts.

2.3 DUST HOPPERS

The dust will be removed from the precipitators by the continuous wet method.

Dust hoppers of steel plate construction shall be provided underneath the precipitators. The plates shall be suitably stiffened and the minimum thickness of the plate shall be 6,0mm. The internal surfaces of all hoppers shall be smooth and have not projections and bracings of any kind on their inside surface on which dust can hold up.

A valley angle of 60° shall be the minimum permissible.

The dust hoppers shall be of a capacity, calculated on a basis of 640 kg per cubic meter of dust, such that they will be able to contain without causing shortcircuiting of the electrodes, or interfering with the efficient and safe operation of any zone of the precipitators, all the dust falling into each of them, when the boiler operates at 100% MGR for a full twenty-four hours, when fired with the basic coal specified in Schedule A.

The mechanical design of each of the hoppers shall be based on a dust load equivalent to a completely filled hopper and a density of the dust of 1000 kg per cubic meter.

Care shall be taken to ensure that cold air and moisture will not infiltrate into the hoppers, thus causing dust removal difficulties due to bridging of the dust.

The casing shall be designed to prevent rainwater from flowing on to lagged hoppers. The hoppers shall terminate at the outlet flange without vertical aided extension pieces above the mouth.

A poke rod agitator or other approved means shall be provided to enable any bridging of dust in the hopper to be broken up.

3.0 CONTROL AND MONITORING EQUIPMENT

3.1 GENERAL

The control and monitoring equipment associated with the precipitators on the boilers shall include control and monitoring consoles, capacity meters, hopper level monitors, chart recorders, alarm panels and all necessary instrumentation to ensure a complete installation.

3.2 PRECIPITATOR CONTROL AND MONITORING CONSOLES

Provision shall be made for the remote control and monitoring of the precipitators associated with the boilers from control consoles to be located either within or adjacent to the existing boiler control desk enclosures on the operating floor level.

A separate console shall be provided for each precipitator and shall contain, as a minimum, the following control and monitoring equipment:

3.2.1 One on/off switch with indication for each electrically independent section of the precipitator.

3.2.2 One meter each for primary voltage, primary amperes, precipitator voltage, precipitator amperes together with a selector switch per meter for switching to any of the electrically independent sections. The signals to these meters shall be 0 to 20 mA and shall be galvanically separate from the quantity being measured with a maximum ripple of 0,5% peak to peak.

3.2.3 Emission monitoring single trace chart recorder with a thirty-day chart and self-inking pen. If more than one trace is required then a second chart recorder shall be provided. Only fault and high level alarm lamps shall be located beneath each recorder.

3.2.4 One alarm lamp per electrically independent section indicating electrical equipment failure, which should cover both the high voltage equipment and hopper meters.

3.2.5 Hopper level high indication for each hopper associated with the precipitator.

TECHNICAL PARTICULARS - POWER STATION

BOILER TECHNICAL SPECIFICATIONS:

  1. Type and model number Boilers 1 & 2 I.C.A.L. 100 MW rating Contract No.10931 Boilers 3, 4 & 5 Mitchell Eng. 100 MW rating Contract No. 7298

  2. Steam pressure Superheater outlet 1271 P.S.I.

  3. Steam temperature Superheater outlet 965ºF {518,3ºC}

  4. Feed water temperature Economizer inlet 405ºF {207,2ºC}

  5. Burner type (P.F.) Boilers 1 & 2 hand tilting, corner mounted Boilers 3, 4 & 5 stationery type, sidewall mounted.

  6. Flame type Pulverized fuel (profile) flame thrower

  7. Method of lowering temperature Attemperator

  8. Heat efficiency Thermal efficiency ±85%

  9. Hot air temperature Air at air heater outlet 503ºF (261,7ºC)

  10. Method layout Rotary air heater, gas heated

  11. Method of ash removal Wet ash removal(hydrovacs and sluice nozzles)

  12. Method of blowing ash Wet ash removal

  13. Exhaust gas temperature Gas leaving the air heater 269ºF (131,7ºC)

  14. Operating level height 35 feet

  15. Outside dimensions – Boiler & 300 ft long x 150 ft wide x 150 ft high Turbine House

  16. Country of manufacture England

  17. Number of Units Five (4)

TURBINE TECHNICAL SPECIFICATIONS

  1. Type and model number Double casing condensing turbine type 11/100220 AEG impulse type

  2. Inlet steam flow (80 MW) Casing I (H.P.) 642920 lbs/hr (373472kg/hr) Casing II (L.P.)527560 lbs/hr (334881 kg/hr)

  3. Inlet steam temperature 510ºC

  4. R.P.M. 3000 R.P.M.

  5. Power output (maximum), heat rate, 100MW continuous maximum rating steam rate

  6. Exhaust steam pressure At 100 MW 1,91 ins Hg 0,066 ata

  7. Exhaust steam flow Through the condenser

  8. Relative internal efficiency 31,1%

  9. Heat consumption rate ± 21 M Joules

  10. Steam consumption rate 113 kg /sec

  11. Number of return stages 6

  12. Extraction pressure at each return stage See chart below

  13. Temperature flow volume See chart below

  14. Process steam extraction press. See chart below temperature and volume

    1. Outside dimensions H.P. Turbine rotor 10514 kg. 1338 dia. 5205mm long

    2. L.P. Turbine rotor 20200 kg. 2520 dia. 5915mm long
  15. Country of manufacture Germany A.E.G.

The turbine is equipped with 6 non-regulated extraction points for feed water heating:

After Pressure Temperature Flow at 80 MW Extr. Stage

Psia (ata) ºF (ºC) lbs/h (t/h) I H.P. 9 236,1 (16,6) 577 (303) 31,090 (14,1) II H.P. 11 139,4 (9,8) 471 (244) 29,320 (13,3) III H.P. 13 76,8 (5,4) 379 (193) 30,200 (13,7)

Extr. Wetness % IV H.P. 15 38,4 (2,7) 0,57 20,060 (9,1)

  1. V L.P. 1 16,1 (1,13) 4,22 23,150 (10,5)

  2. VI L.P. 2 6,3 (0,44) 6,85 28,880 (13,1)

III GENERATOR TECHNICAL SPECIFICATIONS

  1. Type and model Three phase synchronous generator with hydrogen number cooling. Type FKWS 3742 P

  2. Electric resistance Resistances at 20ºC Stator No. 8133 Phase U1 X1 0,00240 ohm Phase U2 X2 0,00238 ohm Phase Y1 Y1 0,00235 ohm Phase V2 Y2 0,00237 ohm Phase W1 Z1 0,00239 ohm Phase W2 Z2 0,00238 ohm

Field winding, slip ring to slip ring Rotor No. 8133 0,119 ohm

Main Exciter No. 704 384 Field Winding I K 5,02 ohm Compoles GH 0,00098 ohm

Amplidyne

No. 338 890 402 Main field iaka 28,1 ohm Control field ibkb 13,2 ohm Diff. field ickc 43,0 ohm

Base Exciter No. 705,805 Field winding CO 16,9 ohm

Field Currents For max. output at 30 psig H 2 pressure approx. 1700 A

  1. Output voltage 10,5 kV ± 5% speed 3000 R.P.M.

  2. output amperage 6,11 KA 50 Hz

  3. Type of cooling Hydrogen H2 cooler type 4 x V15 x 9-2950/2 KF 30203

  4. Country of Germany A.E.G.

manufacture
IV HEAT SYSTEM
1. Oxygen Remover Specifications: Deaerator
Type and model number The manufacturer – Carl Spaeter, Hamburg
Power N/A
Working pressure Full vacuum to 100 P.S.I.S.
Oxygen removal tank volume 8350 imp. gallons
Country of manufacture Germany
Number of units 1 unit per boiler
2. Boiler Feed Pump Specifications:
Type and model number K.S.B.
Flow volume 402 tons/hour
TDH (HEAD)Static head at feed pump suction 166 ft.
Electric motor type and power A.E.I. 2500 H.P. type H.T.A.S. 158132 D2BEIS
Country of manufacture South Africa
Number of units 2 per boiler
3. Condenser Pump Specifications: Extraction pump
Type and model number Condensate pump type C250 (3) A.E.G. make
Flow volume 1503 imp. gal/min
TDH (head) 328 ft. 1 in. W.G.
Electric motor type and power 250 KW A.E.G. type AVK 250
Country of manufacture Germany
Number of units 2 per turbine
4. Turbine heat balance system diagram:Designed by Hamon – Sobelco
Type and model of heat exchanger for each return stage Length 6930 mm Diameter – shell 952mm, Water box 1060 mm
Area of heat exchanger Tube volume 1,2 m3 Refer to drawing No. 035/190 rv.3
V COMBUSTION SYSTEM
1. Blower Specifications: F.D. Fan
Type and model James Howden 22 size 165 Aerofoil
Pressure 17,700 lb/min
Volume290,000 cu. ft/min.
Electric motor type and motor A.E.I. Brush 398 H.P. 5600 volts, 34,7 amps
Number of units Two per boiler
2. Induction Blower Specifications: I.D. Fan
Type and model James Howden TVN3 Radial
Pressure 20,300 lb/min
Volume426,000 cu. ft/min.
Electric motor type and motor A.E.I. 48/40 Brush 1180 H.P. 5600 volts, 89 amps
Number of units Two per boiler
3. Pulverized Coal Feeder Specifications: Feeder
Type and model Mitchell table type
Pressure Mill internal P.A. pressure
Volume25 tonne per hour coal
Electric motor type and motor 3 H.P. 380V 4,5 amp
Number of units 3 per boiler
4. Method of Pulverization : Mill
Type and model of pulverizer P.H.I.
Degree of pulverization (mesh sizes 80% of C.M.R. – 96% through 100 mesh
distribution) 300 H.P. 6600 volts, 23,3 amps
Power consumption 3 per boiler
Number of units
5. Particulate remover specifications: Classifier
6. Combustion system diagram: Refer to drawing Nos. 0,35/7191 Rv. 6, 0,35/886 Rv.4 and 0,35/ 8637
VI FUEL SUPPLY SYSTEM:
1. Pulverizer specifications: Mill
Type and model P.H.I.
Power 6,6 kV x 33 amps
Degree of pulverization 80% of C.M.R. – 96% through 100 mesh
Power consumption 6,6 kV 300 H.P.
Acceptable hardness of coal Hardgrove grindability 55
Number of units 3 per boiler
2. Coal Feeder specifications:
Type and model Mitchell table type
Power 3 H.P. 380V 4,5 amp
Electricity consumption 380 V
Number of units 3 per boiler
3. Coal Conveying Equipment:
Type and model Jeffrey Gallion
Conveyor width 36 inch
Conveyor length various lengths
Number of conveyors (10) ten
4. Screen Analysis Equipment:
Type and model Screen capacity Hand held 12” dia. screen for sample preparation
Outside dimensions
Number of units
VII WATER TREATMENT SYSTEM:
1. 2. Method of treatment, treatment of volume Major Equipment: Design capacity 4 ML/day Sedimentation tanks, sandfilters, pumps, Cation, Anion, mixed bed resin tanks.
Type and model Dowson & Dobson Ltd
Power 2 Potable water pumps 380V 58A = 22 kW each 2 Raw water pumps 380V, 12A = 4,5kw each
Outside dimensions Sedimentation tanks 29 ft2
Number of units 4 Sed. tanks, 4 sand filter, 3 K.B. 2 Cation and 2 Anion
Country of manufacture England
VIII WATER SUPPLY SYSTEM
1. Turbine cooling water inlet and outlet temperature requirements: Inlet 23 ºC, outlet 33 ºC
2. Cooling Water Circulating Pump Specifications :
Type and model Flow rate Vickers Armstrong 54000 gal/min
TDH Hanometric head 56 ft. Static head 27 ft.
Electric motor type and power A.E.I. (AIC 63/42) H.P. 1225 6,6kV, 100 amps
Number of units per turbine One
3. Feed Water Method: Demin. water pumps, Water Plant
Type and model A.G.S.A. Type KL
Flow rate 200 gal/min
TDH 170 ft. head

Electric motor type and power

Number of units per turbine

IX CONTROL SYSTEM

  1. Method of control

  2. Instrumentation types

X ASH REMOVAL SYSTEM

  1. Boiler ash removal method:

    1. Ash Removal Equipment Specifications: Type and model

    2. Capacity Country of origin
  2. Method of ash removal used by the original plant

XI ELECTRICAL SYSTEM:

  1. Voltage steps for plant electricity usage:

  2. Principal transformer Specifications: Type and model Steps Number of units

  3. Plant use transformer specifications: Number of units

Hawker Siddeley D160L. 25HP 2920 RPM 380V 34 amps

4 total

Pneumatic Kent, Bailey, Hannemann

Wet ashing – Hydrovacs and sluice nozzles

Spargo Ash Pump 12” dia. Frame 50

RPM 700, 55m head, 700m3/ hour (water) South Africa No major alterations carried out.

10,5 kV to 6,6 kV Unit transformer 3 phase oil cooled 10 000 KVA 10,5 to 6,6 5

20 Auxiliary transformers 4. Other major electrical equipment specifications:

AEG Electrostatic Precipitator One high voltage transformer Two low voltage transformers TECHNICAL DATA Total weight – 4550 lbs Connection Voltage – 380V single phase Oil Weight – 2410 lbs Frequency – 50 C.P.S. Oil Quantity – 275 gal Input – 41,3 KVA

A.C. Current – 109 amps The no-load R.M.S. value of the Rated High Voltage – 78 kV (peak) H.V. transformer is 55 kV Rated output current – 500 MA And the peak value 55x2=76kV Losses - Approx. 3,6 KW with 380 volt primary voltage.

XII OPERATING INDICES:

Boiler heat efficiency On gross calorific value of fuel 89,3% On net calorific value of fuel 92,6%

Turbine heat consumption rate 510 ºC live steam temp. at turbine combined stop and emergency valves

Steam consumption rate The guaranteed weighted steam consumption including steam to condensate and feed heaters and de-aerator but excluding steam to other auxiliaries and assuming that no water is being circulated between the condenser and the reserve feed tank is:-

Weighted steam consumption As defined by B.S. 132:1951:

3x1 + 4x2 + 3x3 10 …….8.1199 lbs/kWh

consumption at test

loads of 60 MW ……..8.003 lbs/kWh 80 MW ….. 8.047 lbs/kWh 100 MW ….. 8.334 lbs/kWh

Standard coal consumption rate per kWhr 50 ton per hour at 100 MW.

Plant (500 mw) electricity usage rate ± 35 MW.

POWER STATION – EXISTING DATA

PRESENT CONDITION OF PLANT

At present the plant consists of four 100 MW rated steam turbine generator units complete with boiler plant and auxiliary equipment. The units are in a ‘moth-balled’ condition.

AGE

DATE FIRST UNIT COMMISSIONED : 31/03/1963 DATE LAST UNIT COMMISSIONED : DECEMBER 1968

COAL

ANNUAL CONSUMPTION: WHEN GENERATING 1,9 MILLION TONES STOCKPILE VOLUME: WHEN GENERATING 220 000 M3 SILOS/STAITHES: (2) CAPACITY 28 000 TONS BOILER BUNKERS: (15) CAPACITY 500 TONS EACH ASH CONTENT: 20 %

MILLING PLANT

MANUFACTURERS: BOILERS 1, 2 &4 PHI ENGINEERING BOILERS 3 MITCHELL ENGINEERING

MILLS -3 PER BOILER TYPE: BOILERS 1, 2 & TRACK AND TYRE MILLS

BOILER 3 TUBE MILLS

OUTPUT: 22,7 TON PER HOUR, PER MILL (MAX. RATING 25 TONS PER HOUR)

BOILERS

MANUFACTURER: BOILERS 1 & 2 I. C. A. L.

BOILERS 3 & 4 MITCHELL ENGINEERING TYPE: P.F. FIRED, WATER TUBE BOILERS

RATING: 900 000 LBS PER HOUR CONTINUOUS MAXIMUM RATING, AT 1250 PSIG. AND 965 ºF

BURNERS (PER BOILER) 12 UNITS

TURBINES

MANUFACTURER: AEG

TYPE: TURBINE 1 & 2 11/100120

3, 4 & 5 11/100220 RATING 100 MW CONTINUOUS

TURBINE RUNNING HOURS SINCE COMMISSIONING

TURBINE NO 1 155993 HRS 17,80742 YEARS TURBINE NO 2 163585 HRS 18,674086 YEARS TURBINE NO 3 154811 HRS 17,672488 YEARS TURBINE NO 4 144552 HRS 16,501369 YEARS TURBINE NO 5 144826 HRS 16,532648 YEARS

TURBINE G/O HOURS

TURBINE NO 1 16423 HRS 1,8747716 YEARS TURBINE NO 2 9681 HRS 1,1051369 YEARS TURBINE NO 3 32483 HRS 3,7081049 YEARS TURBINE NO 4 6751 HRS 0,770662 YEARS TURBINE NO 5 5727 HRS 0,6537671 YEARS

BOILER RUNNING HOURS SINCE COMMISSIONING

BOILER NO 1 158083 HRS 18,046004 YEARS BOILER NO 2 160604 HRS 18,333789 YEARS BOILER NO 3 152525 HRS 17,411529 YEARS BOILER NO 4 144615 HRS 16,508561 YEARS BOILER NO 5 SOLD

BOILER G/O HOURS

BOILER NO 1 13748 HRS 1,5694063 YEARS BOILER NO 2 22535 HRS 2,5724885 YEARS BOILER NO 3 32483 HRS 3,7081049 YEARS BOILER NO 4 6751 HRS 0,770662 YEARS BOILER NO 5 SOLD

INFORMATION FROM PERFORMANCE MONITORING 31/01/1991 TYPE: WET SYSTEM (HYDROVAC ASHING SYSTEM)

GENERATORS
MANUFACTURER: RATED CAPACITY: TERMINAL VOLTAGE: AEG TYPE FKWS 3742 P 100 MW 10,5 KV
ASH PLANT

PRECIPITATORS

MANUFACTURER: BRAND ENGINEERING (PTY) LTD TYPE: ELECTROSTATIC 5 FIELDS UNITS 1 & 2

3 FIELDS UNITS 3, 4 & 5

GENERATOR TRANSFORMERS

MANUFACTURER: 1 & 2 AEG

3, 4 & 5 OERLIKON RATE CAPACITY: 110 000 KVA TERMINAL VOLTAGE: 10,5/275KV

COOLING SYSTEM

WET SYSTEM THROUGHOUT

COOLING TOWERS (4)

TYPE: NATURAL DRAUGHT, CONCRETE HEIGHT: 93,4 METRES

CHIMNEYS (2)

HEIGHT: 119,48 METRES TYPE: SINGLE FLUE - CONCRETE

MOTHBALLING DATES

UNIT NO 1 08\01\1987 UNIT NO 2 14\09\1988 UNIT NO 3 18\10\1989 UNIT NO 4 10\09\1990 UNIT NO 5 05\11\1990

RUNNING PARTICULARS AT SITE - ESTIMATED BOILERS

Pounds per hour evaporation 720,000 830,000 900,000 corresponding 113,6kg/hr to 100 MW 80% rating M.C.R. Temperatures Water from economizer (inlet 405 ºF)……………….ºF 535 535 537 Steam at superheater inlet……………………………ºF 580 584 588 Primary superheater outlet ….……………………….ºF 833 849 857 Secondary superheater inlet….………………………ºF 805 806 807 Superheater outlet ……………………………………ºF 965 965 965 Air at airheater (minimum)…………………… …….ºF 90 90 90 Air at airheater outlet………………………….......... ºF 491 503 504 Gas leaving furnace………………………………….ºF 2018 2088 2130 Gas at superheater inlet ……………………………..ºF 1972 2042 2084 Gas at superheater inter-stage …. …………………ºF 1725 1782 1824 Gas leaving superheater ………………………..........ºF 1059 1081 1111 Gas at economizer inlet …………………… ……….ºF 1059 1081 1111 Gas leaving economizer (Blr.1………………………ºF 813 825 838 (Blr. 2…………...................ºF Gas leaving airheater (minimum) … ……………......ºF 260 269 280

Pressures

Steam in saturated steam drum lb/ sq. in………… 1337 1365 1385

Steam drum (Cont.)

Total discharge capacity saturated steam ……………………………………..940,000 lb/hr.

Superheater

Type ………HOPKINSON’S “HYLIF TORSION BAR………...............3 Bore ………………………………………………………………………2½ ins.

Total area …………………………………………………………………….. 6.85 sq. in.

Total discharge capacity superheater steam………………………………….. 291,000 lb/hr

(The contractor should note the special requirements of the South African regulations with regard to safety valve areas.)

SAFETY VALVE BLOW-OFF PRESSSURES

DRUM SUPERHEATER NO. OPEN CLOSE NO. OPEN CLOSE

1. 1520 1475 1 (Elec: assisted) 1,330 1,290
2. 1530 1485 (unassisted) 1,350 1,290
3. 1530 1485 2 1,350 1,310
4. 1540 1485 3 1,355 1,315

RUNNING PARTICULARS AT SITE (CONT.) BOILERS

Pounds per hour evaporation 830,000 900,000 720,000 corresponding to 100 MW rating

B. Th. U. absorbed

Per sq. ft. boiler surface ………….per hour 89,800 103,900 112,900

Per sq. ft. superheater surface ……per hour 5,560 6,440 7,265

Per sq. ft. economizer surface (Blr. 1) per hour 2,170 2,488 3,265

Per sq. ft. airheater surface …………per hour 542 623 676

B. Th. U released per cu.ft. of combustion chamber volume …… per hour 14,530 16,810 18,210

Velocities (average)

Water through economizer tubes (Blr. 1) f.p.s. 2,2 2,5 2,7 (Blr. 2) f.p.s. 3,7 4,3 4,7

Steam through pipes connecting drum to superheater ………………......f.p.s. 43,2 49,8 54,0

Steam through primary S/H tubes …………………………………..f.p.s. 56,2 63,5 70

Steam through secondary S/H tubes …………………………….. f.p.s. 103,9 117,0 120,6

Air through airheater ……………… f.p.s. 20,6 23,8 25,8

Estimated heat losses

Drygas………………………………………… 4,11 4,23 4,55

H2 plus H2o in fuel ........................................ 3,75 3,79 3,79

Unburned combustible………………………… 1,91 1,98 2,03

0,63 0,70 0,73Radiation …Unaccounted

Total heat loss ……………………………. 10,40 10,70 10,90

Overall efficiency (%) of unit before deducting of auxiliary power
On gross calorific value of fuel………………. On net calorific value of fuel ………………… 89,6 92,9 89,3 92,6 89,1 92,4