Circular July 2008
Tuesday, July 08, 2008
Dear Sirs
subject to prior sale we can offer
1.) 12.5 MW
complete Biomass Power Plant
Manufacturer: Westinghouse Turbine and
Generator (1953 vintage), Zurn Boiler
(original boiler at construction)
Year of Construction: Facility in
1983
Running
hours: It ran at approximately 93% to 97% capacity from 1983 to 2002
Location: USA
TURBINE-GENERATOR - SPECIFICATIONS
CLASSIFICATION: 1953
Westinghouse Condensing, Extraction, Impulse Turbine driving a Two-pole AC
Generator at 3600 RPM.
UNIT RATING: By design, the
limitation of the turbine-generator unit is the limitation of the prime mover -
the turbine. Thus, maximum output is 12,650 Gross KW.
TURBINE RATING - STEAM
PRESSURE: 600 PSIG
STEAM TEMPERATURE: 825 degrees Fahrenheit
STEAM FLOW: 125,000 LB/HR
EXHAUST PRESS.: 1.5 Hg
KILOWATTS: 12,650 kw
STEAM VARIATIONS
PRESSURE: The initial steam pressure
at the turbine throttle valve inlet shall not exceed 600 psig average over a 12
month period of operation at rated load. At reduced load the average should not
exceed 630 psig. Absolute maximum inlet pressure in abnormal situations is 780
psig (aggregate duration of this pressure not to exceed 12 hours per 12 month
period).
TEMPERATURE: The initial steam
temperature at the turbine throttle valve inlet shall not exceed 825 F average
over a 12 month period. Absolute maximum inlet temperature in abnormal
situations is 875 F (at this temperature, limit is 15 minutes duration per
swing and aggregate duration not to exceed 80 hours per 12 month period).
GENERATOR RATING -
VOLTAGE: 12,500 AC
AMPERAGE : 625
POWER FACTOR: .85
FREQUENCY: 60 Hertz
KVA 13,529
EXCITER RATING -
VOLTAGE: 250 DC
AMPERAGE : 260
TURBINE INFORMATION
THROTTLE VALVE: The throttle valve is
hydraulically operated to control the flow of steam to the turbine during
start-up. Turning the valve wheel repositions a valve that controls the flow of
high-pressure oil into the operating cylinder. The operating cylinder is used
in conjuction with the low oil and overspeed trips on the unit.
STEAM CHEST: The turbine governor controls
the steam chest first stage nozzle valves. The valves seats are of the diffuser
type. Partial-load operation is more efficient this way due to the reduction of
throttling losses.
BLADING: 1 - CURTIS (VELOCITY COMPOUNDED)
13 - IMPULSE
3 -
PAIRS OF ROWS OF REACTION BLADING
The major
difference between impulse and reaction blading is the shape of the blades. By
design, impulse blading gets a pressure drop, and thus work, accross the moving
blades only. The fixed blading, or diaphragms serve only to redirect the steam.
With reaction blading, there is a pressure drop accross the fixed and moving
blades. Therefore, reaction blading is usually used in the low pressure end of
a turbine before entering the condenser. Although work is done across fixed and
moving blading, reaction blades are less efficient than impulse.
EXTRACTIONS: There are four extractions on
this turbine for heat exchanger and gland seal supply steam. For more
information, see Specs - Boiler / Steam
ROTOR GLANDS: The glands are of the
Labyrinth-type. Multiple spring-back seal rings maintain very close clearance
to the turbine rotor. Steam at approximately 1 psi is supplied to the high and
low pressure glands to further seal the clearances. The gland at the low
pressure prevents air from leaking in. The gland at the high pressure end
prevents steam from leaking out.
GENERATOR INFORMATION
A generator has three requirements: 1) A
magnetic field, 2) a conductor, and 3) relative motion between the two to cut
flux and produce electricity. The Bio Energy generator consists of two
generators. The exciter which produces DC power and the generator which
produces AC power (an AC generator is also called an alternator). The generated
DC voltage of the exciter, (usually in the 100 - 150 DC V range at 120 - 170 DC
A), supplies the magnetism to the generator 2-pole rotor. The stator, or
stationary windings, of the generator are the conductors.
A General Electric current limiting
reactor is installed to prevent the destructive flow of energy that may be
caused by a short circuit or overload. A multitude of realys are also
interlocked to protect the generator and exciter from abnormal conditions.
Cooling for the generator is provided by
two water cooled heat exchangers that run the length of the unit on both sides.
The exciter and collector are cooled by a shaft driven fan which takes suction
and discharges to the area below the unit.
Price: 3,850,000.- USD
needs to be removed from the site.
Detailed information as Scope, Drawings,
Pictures, Calculations etc on request.
For
more information ask by Email
Added A.) Gas Turbine (G 24 heavy fuel oil/ crude oil),
Generator (40 MVA)
now only 8 units left!!
This offer provides for the delivery
of Power Plant Equipment with currently 12 (now only 8 units left!!) units
of 25 MW electrical output each. The minimal offer consists of the supply of 4
groups, each including Gas Turbine (G 24 heavy fuel oil/ crude oil), Generator
(40 MVA) and related auxiliary equipment.
1. Technical
Data
1.1
Performance Data per Equipment Group
·
Design
heavy duty, easy to maintain
· Electrical
Output
~ 25 MW
·
Efficiency
~ 24 %
· Turbine Inlet
Temperature
750 ° C
· Turbine Outlet
Temperature
340 ° C
· Generator
Voltage
10.5 kV
·
Frequency
50 Hz
· Fuel
Consumption
~ 9.3 t/ h
· Calorific Value of
Oil
~ 40 000 kJ/ kg
Fuel
· Liquid
Fuel
Heavy Fuel Oil/ Crude Oil
Generator
· Output
40 MVA
·
Speed
3 000 RPM
·
Voltage
10.5 kV
·
Enclosure
IP 54 ICW 37
· Insulation
System
F
·
Excitation
static
Start-up Motor
·
Output
2.5 MW
· Voltage
6.3 kV
Main Transformer
·
Output
40 MVA
·
Voltage
10.5/ 6.3 kV
110 kV
Auxilaries
· Lubrication
System
· Control
System
· Instrumentation
· Fuel
System
· Electrical
Equipment
· Spare
Parts
Additional Data
· NOx
Emission
< 500 ppm
· Manufacturer
Bergmann- Borsig Berlin
· Number
of
Machines
6
· Location
Germany
· Operating
Time
average 4 000 h
· Starts
average 2 000
· Time
for
Dismantling
~ 1 month
· Time
for Shipment
depending on new Site
· Time
for
Erection
~ 3 months
· Layout
located on Steel Foundation in a Power House
· Weight
~ 350 t
2. Commercial Data
2.1 Basic Equipment
Gas Turbine
and Generator (approx. 3 000 h) together with
Auxiliary Equipment as per
Technical Data
Description
2.70 Mio € each
2.2 Scope of Services
2.2.1 Test/ Dismantling/
Packing
Expertise and Electrical Test of
Generator
Dismantling, Packing for
Seafreight
Transport and Insurance to German
Port
0.800 Mio € each
Time required for dismantling,
packing and transport to
German harbour approx. 6 weeks for
4 Units.
2.2.2 Maintenance Issues
New Air Filters
Noise Dampers
Stacks
State of the Art I&C/ New
Turbine Controller (no Control Room)
Fuel Heating
Device
Price 1.480 Million Euro each --- PRICE NEGOTIABLE!!
Added B.) (7) x 5.6 MW, De Laval Generator Sets
13.8 kV, 3 phases, 60 Hz, 450 rpm
Diesel Engine
Manufacturer De
Laval Enterprise, USA
Model DSRV
16-4
Type Four-stroke-cycle,
Turbocharged, After-cooled
V-type with Trunk-type Pistons, Stationary
Diesel
No of Units Seven
(7)
Rated
Output 8905
Hp (6643 kW)
Dependable
Capacity 7506
Hp (5600 kW)
Speed 450
rpm
No
of Cylinder 16
Cylinder
Bore 17
inches (430 mm)
Piston
Stroke 21
inches (530 mm)
Specific
Fuel Rate 50%
- 0.378 lb/BHp-hr (0.230 kg/BkW-hr) (HFO)
75% - 0.371 lb/BHp-hr (0.226 kg/BkW-hr) (HFO)
100% - 0.384 lb/BHp-hr (0.233 kg/BkW-hr) (HFO)
Total Length 232
inches (5890 mm)
Width 180
inches (4572 mm)
Height 150
inches (3810 mm)
Total
Weight Approximately
250,000 lbs (113 tons)
Fuel Bunker C
(continuous)
Distillate (start and stop)
Heat Rate each
6736 Btu/BHp-hr (9029.5 Btu/BkW-hr)
Fuel
Heating Steam
from Waste Heat Recovery Boiler
Type
of Control Automatic
(PLC, GE Fanuc), Remote
Generator
Manufacturer Electric
Machinery/Dresser Rand
Type Brushless
Synchronous Generator
No
of Units 10
units
Rated
Capacity 8.019
MVA / 6.415 MWe
Dependable
Capacity 5.400
MWe
Rated
Voltage 13.8
kV
Rated
Current 335
Ampere
Rated
Speed 450
rpm
No
of Phase 3
Frequency 60
Hz
Power
Factor 80%
< Short Story >
Complete set with all auxiliary equipment (Please refer to
pictures)
Overhaul History : In 1997, all these generator sets had been
overhauled in the original manufactory (De Laval Enterprise) and with
Certification of overhauled
YOM : 1973
Running hours : about 41000 hours (total), 40000 hours (after
overhaul)
Since 1973, these Gen-sets were working in a
mine total 1000 hours (only for tested running) and then the mine was disused
by government later. Since 1997, A National Power Plant purchased all of the
sets as used equipment. Based on the national law rule, all the Gen-sets must
have a overhaul certificate from the original manufactory, either new or used.
So they hired the original manufactory (De Laval Enterprise) to overhaul all of
the Diesel Engines and the Alternators, and upgraded the generator sets with
PLC of GE FANUC. So, the total running is about 40000 hours from 1997 until
2004.
Quantity available for now : seven (7) sets
of 6643 kW (rated output)
Current Location : South East Asia
|
|
|
|
|
|
|
|
|
|
|
|
Price: 4,120,000.- USD
Added C.) 36.5 MW PG6471-B GT
Gas turbine brand Nanjing
Turbine JV GE
GT country of origin China
GT model PG6471-B
date of Manufacture 1994
running hour 29845
rated output power MW 36,5
GT fuel HFO, diesel
last date of overhaul July.2004
hour left until next overhaul 15000 hours
number of start up 2057 times
turbine control Mark IV
generator maker Nanjing Turbines Works
generator model QFR-36-1
generator output voltage 10 kV
output frequency 50Hz
control Hz
generator output power 36000kW
diesel start up engine Detroit V71T 630hp
HRSG Harbin Boiler Factory
boiler output 65T 3.82MP 445C
steam turbine maker Nanjing Turbine Factory
steam turbine model QF-15-2 , output power 15MW
gear box TP3000
control panel 1 set
air inlet system 1 set
exhaust system 1 set
CO2 panel 1 set
high voltage switch panel GG-1A(F)2-03
main transformer SF8-63000/110
plant transformer SF 1250/10
Added D.) 16 MW Caterpillar 3616 Diesel Power
Plan
(4) x 4 MW
11 kV, 750 rpm
Make & Model : Caterpillar, 3616
Installed in 1996
Working hours : 20194, 20358, 19321, 21980
Alternator:
Make : AVK, Germany
Type : DIDBV P/8
No. : 8418138A002
50 Hz,, 5163 kVA each
750 rpm, 3 phases, 11 kV
EXCT
44 V, F Class, IP 23, K752.2.23, 85V, 200 Hz, 20 tons
1250 W, 220 V, 3.6A
Make : 1995
CAT 3616
BHP 5793, 750 rpm, 4320 kW
C/S 50
, 5163 kVA, 11 kV
Year : 1995
Fuel Consumption : 0.057 gallon per kWh
Including:
Engine : 4 units
Alternator : 4 units
Cooling Towers
Lube Oil Filters
Exhaust System
Control Panels
Synchronizers
Other related Panels
Auxiliaries
Fire Fighting and other Controls
Price for the complete Plant : 2,398,000.- USD
as is where is
|
Added E.) 3 x 5.2 MW Model #18KU30A Mitsubishi Generator Sets Three Mitsubishi 5.2MW generator. year 2003 5000kw 6600kva 60Hz Hours: 10,000 - 15,000 each 3 sets $660,000.00 each As is where is (Complete with Fuel Treatment Module) More pictures on request |
|
|
Added F.) 30 MW Sulzer
Power Plant, 60 Hz
with complete auxiliaries
and spare parts.
Please note that the units
were installed in early and middle part of 90's..... well maintained.
I. ENGINE:
Make
Z.U.T. ZGODA SULZER (Poland)
Model 12
ZV 40/48
Serial
numbers 50612
Nominal
Power of Diesel Engine 6180 kW (measured at shaft under ISO conditions)
Number of
strokes 4 (four)
Cylinder
Power 550 kW/cylinder
Number of
Cylinders 12
Nominal
speed 514 rpm
Maximum
power in one hr 7260 kW (during 12 operating hr. each)
Piston
Diameter 400 mm
Piston
stroke 480 mm
Cylinder
capacity 60.82 L/cylinder
Effective
pressure 1.99 MPa.
Combustion
pressure 12.8 MPa
Average
piston speed 8.224 m/s
Flywheel
effect (W*R sq.) 4.94 Tm?
Note:
The
nominal power of the Engine corresponds to the operating instructions of ISO
3046.
Under the
above conditions and assuming a calorific value of 42.707 kJ/kg, the specific
fuel
throughput
is as follows:
100% load
201 g/kWh + 5%
75% load
201 g/kWh + 5%
50% load
205 g/kWh + 5%
Lube-oil
consumption - the consumption in the lube system of the working face of the
Cylinders
amounts
to 80% of the total consumption
Amount of
heat dissipated by the Engine : 290 kW
Combustion
air consumption under nominal conditions : 52,500 kg/hr
Air
cleaning (by means of NSA filter) : up to 5 g/m3 solids
Mass of
Exhaust under nominal conditions : 53,800 kg/hr
Temperature
of gasses after turbo compressor under nominal conditions : 340 0C
Noise
level at suction and exhaust sides after silencer : 85 dBA
Operating
parameters stable minimum speed : 320 rpm
Admissible
operating duration at no load : 30 min.
A)
Barring Gear (Turning Gear)
B)
Turbocharger (Left & Right)
C)
Air-cooler (Left & Right)
II.
GENERATOR
A)
Brushless AC Generator
Make
Ideal Electric, (OHIO, USA)
Model
Type SAB
Capacity
7500 kVA (6000 kW)
Frame
M8-31
Voltage
13,800 V
RPM 514
Amp. 314
Phase /
Hz 3 / 60 Hz
Wire 6
Duty
Continuous
Power
factor 0.8
Class
Ins. F
Temp.
rise 105 0C
Rise by
Res. Amb. temp. 40 0C
B)
Brushless Exciter
Type FRBA
Frame BE
16-6
kW output
50
DC volts
/ Amp. 250 V / 200 A
Class
Ins. F
Fld.
Volts / Amps. 125 V / 8.8 A
Temp.
rise 80 0C
Exciter
surge prot. B57826-GR1
Rectifiers
qty. 3 no. B-54922-F, no. B-54922-R
C)
Permanent Magnet Alternator
III. AIR
SYSTEM
1) Suction
Air
A) Locker
Air-Maze Heavy Duty Oil Bath Air Filter (2 Units)
B) Air
Suction BR
C)
Expansion Bellows
2) Control
Air Equipment
A) Air
Bottle
B)
Condensate Drain
C)
Pressure Reducing Valve
D) Air
Dryer
E)
Automatic Drain Valve
F) Filter
IV. WATER
SYSTEM
1. Raw
Water System
A)
Cooling Tower
B) Raw
Water Pump (Running)
C) Raw
Water Pump (Spare)
D) Raw
Water Strainer
2. Jacket
Water System
A) Jacket
Water Heat Exchanger (Alfa Laval)
B) Jacket
Water Thermostat (AMOT)
C) Jacket
Water Pump (Running) (Ajax Elite)
D) Jacket
Water Pump (Spare) (Ajax Elite)
E)
Circulating Pump (Ajax Elite)
F) Jacket
Water Expansion Tank
3. Nozzle
Cooling Water System
A) Nozzle
Cooling Water Pump (Running)
B) Nozzle
Cooling Water Pump (Spare)
C) Heater
V.
LUBRICATING OIL SYSTEM
A) L.O.
Separator Module (LOPX 707)
B) Feed
Pump (running)
C) Feed
Pump (spare)
D) Pre-Lube Pump
E) Oil
Cooler
F)
Lube-Oil Filter (Boll and Kirch Auto back-flushing)
G)
Indicating Filter (Boll and Kirch)
H)
Thermostatic Valve (AMOT 6BO)
I)
Cylinder Lube-Oil Tank
J)
Lube-Oil Sump Tank
K)
Lube-Oil Sludge Tank
L)
Lube-Oil Sludge Tank Pump
VI. FUEL
OIL SYSTEM
1.
Three-way Valve for HFO/MDO
2. Supply
Pumps
3.
Pressure Control, Overflow Valve
4. Flow
Meter
5.
Deaeration System
6.
Circulating Pumps
7. Steam
heat exchanger
8.
Electric heat exchanger
9.
Viscosity transducer
10.
Filter Arrangement
11. Alarm
Cabinet
12. Fuel
Sludge Tank
13. Fuel
Sludge Tank Pump
VII.
EXHAUST SYSTEM
A)
Silencer (rolled plate)
B) Smoke
Stack (rolled plate)
C)
Ducting
D)
Expansion Bellows
Price 4,340,000.- USD
2.) 7.6 MW Cogeneration Gen-Set (MAN B&W
Holeby):
The power plant equipment subject to this quotation is
a currently running power plant which is newly overhaulled and in well condition
for operation in though site conditions. The unit can easily burn fuels with
viscosity up to 700 cSt. The engine MAN B&W Holeby 18V28/32H is the most
reliable engine of its class and range. The engine speed is 750 rpm which
provides low maintenance costs and higher reliability. The reason for the
operator to sell the plant is that HFO No.6 is no more cheap in the country
where it is located. Besides the gen-set; all relevant tanks, pipings, and
necessary equipments including the electrical switchgear is included in the
scope of supply as this is a currently operated power plant.
Please be
informed that the unit shall be uninstalled from the current location,
transported and installed in new site in 5 - 6 months which means a short
period for such power plants, it is not possible to provide the new plants of
the same range with the same type of engine in a shorter time than 9-12 months
which is a long term.
1)
GEN-SET (MAN B&W Holeby):
2 pcs MAN B&W Holeby Engine + 2 pcs of AVK Alternator
+ Complete Control System
Working Hours : 30.000 hours(first gen-set), 31.000
hrs (second gen-set)
Latest Overhaull at : 28.500 hrs(first gen-set),
29.500 hrs (second gen-set)
Engine Output (Continious Power): 3960 kWe
Alternator Output : 3800 kWe
2)
Fuel System
-
2 pcs of Fuel Supply System (Booster Module) which can either feed diesel oil
or crude oil or heavy fuel oil up to 700 cSt viscosity. This provides a high
fuel flexibility. MAN engines can easily burn such fuels of variable fuels
while other engine makes can not.
-
2 pcs. Fuel Separators.
-
2 pcs of Fuel Oil Filling Pump (For filling the Fuel Tank)
-
2 pcs of (No.6 Fuel Oil) transfer pumps
-
Fuel Oil Storage Tank
-
Fuel Oil Buffer Tank
-
Fuel Oil Service Tank
-
Waste Oil Tank
-
Sludge Tank
-
Diesel Oil Service Tank
-
The sludge separators can separate the waste fuel oil(sludge) and regain some
of the fuel and can additionally burn it in the engine thus saves an amount of
fuel and reaches an increased system efficiency.
3)
Lubricating Oil System :
-
2 pcs of Lubricating Oil Separator
-
Lubricating Oil Storage Tank
-
Lubricating Oil Transfer Pump
4)
Cooling System:
-
2 pcs of cooling tower
-
2 pcs of cooling water circulation pump
-
2 pcs of Expansion Tank
-
2 pcs of Chemical Dosing Tank
5) Pressurized
Air System :
-
1 pcs of pressurized air compressor working at 30 bar
-
2 pcs of Pressure Reduction Valve(One is the spare for the other) 30/9 bar
-
Pressurized Air Tank (30 bar)
6)
Exhaust/Combustion System :
-
Exhaust ducts , steel construction supports for exhaust ducts , chimney , steel
construction supports for the chimney
-
2 pcs of waste heat recovery boiler with a capacity of 1,000,000 kcal/h which
can produce 1,5 Tons/h of steam at 7 bars.
-
Air Ducts before Turbocharger, Expansion Joints , Steel Structure Supports for
Air Ducts.
-
Heat exchangers for recovering the heat of Engine HT jacket cooling circuit.
7) Control
–Commanding Pannels , Gen-Set automatic commanding and monitoring system with
SCADA and PLC.
8) 110
/ 24 V UPS
9) 2
pcs of Ventilation Fans(1 for each gen-set) for the power plant building
ventilation
10) Overhead
crane ( capable of carrying any load not bigger than 2 tons, 3 axis type,
it helps a lot at times of removal or installation also at future maintenance)
Note: The
building is steel construction and if it is required and seen feasible by the customer
it is also possible to be transported to the new site.
The net output of each gen-set is 3,8 MWe , The Net Total (Alternator) Ouput of
the Power Plant is 7,6 MWe. In hot weather conditions this output shall
be lower.
Price 1,950,000.- Euro
For
more information ask by Email
3.) 2x5MW Mitsubishi Diesel Power Plant
Manufacturer : Mitsubishi Heavy Industries Ltd / Yokahama
–Japan
MODEL : 16 KU30 A
POWER: 10 MW (2 x 5 MW)
Manufacturing Year : 1996
Commissioning Date: July 1997
Total Working Hours : 47.000 saat
Fuel : No:6 Fuel Oil and Diesel
Total Power Production per year : 383.717.420 kwh
Cooling Capacity : by Absorption chiller (1,350,000 kcal/h)
Heating Capacity : By Stack Heat Exchanger (1,762,000 kcal/h)
Status of Maintenance and Operation : The major overhaul is carried out on
14/04/2003.
After 1/05/2003 turn-checks are done weekly.
|
Equipment |
Qty. |
|
Diesel Gen-set |
2 |
|
Stack (Φ 1,2 x |
1 |
|
Cooling
Tower ( Alarko ARK-10, 925.000 kcal/h) |
8 |
|
AEG,
11/33 kV,50 Hz, 15 MVA step-up transformer |
1 |
|
Complete
control and distribution panels |
1
set |
|
Tanks |
|
|
Fuel
Oil tank (Φ7 x 7
mt, |
2 |
|
Diesel Oil Tank ( |
1 |
|
Clean Oil Tank ( |
1 |
|
Waste Oil Tank ( |
1 |
|
Sludge tank ( |
1 |
|
Pressurized
Air Tank (25 bar, |
3 |
|
Separators and Separator Spares |
|
|
Lub-oil
Seperator ( Westfalia OSA 7-0136-066) |
2 |
|
Fuel
Oil Seperator (Westfalia OSA 20-02-066) |
2 |
|
Sludge Seperator ( Westfalia ESC
4-01-066) |
1 |
|
Crane (2,5 T, overhead crane) |
1 |
|
Pumps |
Various |
|
Fans
(Edvan NEP90/112-SL 90-K) |
6 |
|
Exhaust Gas Heat Exchanger |
1 |
|
Absorbtion Chillers |
2 |
|
Spare parts |
Various |




|
|
|
|
|
|
|
|
|
|
Price: 2,850,000.-
USD For more information ask by Email

4. ) 3 x 1.1 MW Caterpillar
Gen.Sets
already in container
type g 3516b model natural gas
1165 kw / 50hz / 1500 rpm
with 11 sm g-36 merlin gerin
med. voltage cells (schneider electric)
with 3 ABB trafo step up 34.5 / 0.4 kv 1600 kva (oil type)
heat recovery
system
boiler, heat exchange

CONTROL SYSTEM / SYNCHRONIZATION
UNIT
Working hours :
1- 15.070
2- 15.761
3- 17.511
W,TH 1 EACH Hilkar Neutral
Resistance 20 Ohms, 1000 Amp.
Price: 950,000.- Euro
For
more information ask by Email
5.) Ruston TB
4000 Gasturbine
* gasturbine type Ruston TB 4000
* electr. Power 3,38 MVA
* running hours less 800
* starts 800
* frequency 50 Hz
* year of manufacturing 1976, overhauled in 1994,
modification of the control system in 1998
* including turbine control, generator, gearbox,
lubrication oil pump,
fresh air filter housing, automatic synchronisation,
spareparts for control system, new fuel gas control
system
regulator from1996, battery system for the lubrication
oil
system and turbine control, housing.
This plant is used as an emergency plant and very well
maintained and the owner
invested much money in the past for overhaul and
modifications. The plant is still
available in running condition and can be inspected
any time.
Price: 425,000.00 EURO ( incl. dismantling, packing,
loading, transport FOB )
For
more information ask by Email
6.) Several new unused Frame 9'S
Fuel: Set up for Liquid Fuel (DIESEL
2).
GE Frame 9 Gas Turbine Packaged Power
Plants
PERFORMANCES: SIMPLE CYCLE
Output
Power: 126 MW
Heat
Rate: 10096 BTU/KWh (10650 kJ/kWh) (natural gas)
Model
Structure
Type
Standard Standard
Standard
Fuel
Natural
Gas Distillate Oil Heavy
Oil
Output
126100 kW 123300 kW 115300 kW
Heat
Rate(LHV) 10650 kJ/kWh 10730 kJ/kWh 10960 kJ/kWh
Heat
Cons(LHV) 1343×106 kJ/h 1328×106 kJ/h1263.7×106 kJ/h
Exhaust
Temp 543 543
520
Exhaust
Flow 1505×103kg/h 1509×103kg/h 1508.6×103kg/h
Shaft Speed 3000r/min
3000r/min
3000r/min
1-year of manufactured: 2007
2-location: Europe
3-how many hours working NONE - these are NEW -
unused.
4-guarantee At this stage, warranty will only provided
under an O&M contract.
SCOPE, LIMITS AND EXCLUSION FROM THE SUPPLY
Scope of Supply
1. Gas turbine
generator package
2. Mechanical
• Gas Turbine
• Air
Compressor
• Combustors
• Turning and Reduction
Gear
• Air Inlet
facilities (Filters and Ducts)
• Exhaust
facilities (Ducts, Silencer) (less exhaust elbow )
• Starting
Motor system
• Dual Fuel
Combustors
• Lube and
Control Oil System
• Closed
Circuit Cooling Water system
• Atomizing and
Cleaning system
• Instrument
Air system
• Enclosures,
including HVAC, Fire-fighting, Electrical Switchboard for:
- Gas turbine
unit (external and internal)
- Gas turbine
auxiliaries
- Electrical
Switchgear
- Control
- Closed
Circuit auxiliaries
- Water Injection
• GT
Supervision, Control and Protection Systems
• Fire Fighting
(detection and protection) system
• Gas Detection
system
• Thermal
Insulation and Lagging
• Compressor
Washing and Cleaning facilities
3. Electrical
• Electrical Generator,
auxiliaries and related equipment (Circuit Breaker,
Grounding
Switch, Bus duct, Neutral Grounding cubicle, etc.)
• Starting
Motor system
• Unit
Transformer (11/6 kV) and auxiliary MV/LV Transformers
• Main
Switchboards (6 kV, 380 V PC, 380 MCC and emergency MCC) and MV
isolated bus
ducts
• Auxiliary
Switchboards (Generator Protection, HVAC, Fire-fighting, Lifting
facilities,
etc)
• 110 DC Power
System
•
Uninterruptible Power System (UPS)
• AC/DC
Electrical Motors (DC Motor starters included)
• Electrical
Protection system
• Lighting and
Motive Power system, Heat tracing, Grounding, etc.
• Cables and
Cable Trays
4.
Instrumentation & Controls
• On board
Instrumentation
• Instrument
Panels and Junction boxes
• Control,
Protection and Monitoring Panels
• MMI
(man-machine interface)
5.
Miscellaneous
• Special Tools
• Anchor Bolts
and Plates
• Stair and
Ladders
• Steel
Structures
6. Special
Tools and Maintenance equipment (for the above mentioned machinery)
7. Operating
and Maintenance Manuals
PERFORMANCES: SIMPLE CYCLE
The following
Gas Turbine performances:
ISO Conditions
With reference
to the following conditions:
Ambient
Pressure: 1013 mbar
Ambient
Temperature: 15 °C
Relative
Humidity: 60 %
Gas Turbine
Inlet/Exhaust Pressure drop: 89/127 mm H2O
The Plant
Performances at Generator terminals when the plant is operated at GT new
and clean conditions shall be:
Base Load
Output Power: 126
MW
Heat Rate: 10096
BTU/KWh (10650 kJ/kWh) (natural gas)
Price: For more
information ask by Email
FULL SCOPE ON REQUEST Back to Homepage
7.) One ( 1 ) Used low hour 100 Mw Coal
Fired Powerplant
STG
Sets Complete With Boiler Plant
·
Fuel: Fired
On Either Pulverized Coal Or Fuel Oil
·
Cycle: 50Hz
·
Rated Output: 100 Mw Each Unit
·
Operating Hours: 144000
·
First Commissioned: 1968
·
Condition: Excellent
·
Fuel: Pf
Coal Or HFO (Or Gas)
·
Boilers: Ce And
Mitchell, Ta Sets Are Aeg Germany
·
Operating Pressure: 1275
PSIG.
·
Final Steam Temperature: 965F
·
Specific Steam Consumption Of
Turbine: 4 Kg / 1 Kwh
·
Operating Pressure: 1275
Psig. / 965 F
·
Steam Consumption/Required
Pressure: 82 Barg Hp Inlet Steam, 525 Deg. C, 4,1
Kg Steam / Kwh, Includes Steam For All Feed Heating And De-Aerator
·
Required Tie-Ins For Steam TG: Units Are Complete, Tie-Ins Required For Main Steam,
Cooling Water For Condenser, And Piping For Feed-Water Heating System Available
Complete With Valves, Condensate Extraction Pumps, Cooling Water Pump And
Valves, Transformer 110 Mva, 300000 Hv, 15000 Lv. +- 5%
·
Manufacturers Original Data (Catalogue) Manuals
Including Drawings
·
Steam Turbine Performance And Characteristics Manuals
Plant Comes Complete With:
·
Buildings
·
O/H Crane For Turbine Hall Etc
The plant was
kept mothballed under supervision for start-up since 91; there was a serious
drought in the area
which left the plant without cooling
water for the condensers. Once the water situation improved, the supply
of power from the smaller power stations was no longer required at the
time since the big stations
(up to 4800 MW) were running on ECR. (Economical Cont. Rating). In 1999
the decision was made to sell,
first to local interested parties, later to overseas prospects.
The equipment has been professionally laid up.
Price:
7,500,000.- USD
Still
installed, removal & install not inluded.
For
more information ask by Email
8.) 10 units Komatsu 545kw
in tandem
produce 5.45mw of Power.
The equipment
is now dismantled (very professionally) and is stored at docks.
Engineers are at hand to reinstall at an extra cost.
They are all completed with control system, silencer,
and even exhaust gas collection boiler as co-generation system. This plant can
function as a power station of 5,450kw, not only as per unit. All pipes necessary
for power station can be joined if requested.
Price
1,500,000.- USD for a quick sale.
The original
cost of the equipment in 2006 was over 10 million USD.
The equipment
has done less than 4 months work.
|
|
|
|
|
|
|
|
|
|
For more information ask by Email

9.) 105 MW Siemens Gas Turbine Plant
still
installed
Complete
Gas turbine Power Plants each consisting of One Siemens gas turbine and
all relevant auxiliaries in excellent condition, fully operable, ready for
immediate delivery.
Currently
on liquid fuel
Description
of Gas Turbine Generators
Siemens
V94.2 heavy-duty gas turbine. rated output of 105 MW at ISO conditions.
The
GT unit is of single-shaft, single casing design, equipped with 2 silo-type
combustion chambers, a 16-stage compressor and a 4-stage turbine. An air-cooled
generator, rated at 125 MVA and generating at 10.5 kV is driven from the cold
(compressor) end of the GT unit. –
Siemens V94.2 heavy-duty Gas Turbines with all relevant auxiliaries in
excellent condition
10.5 KV, 50 Hz
Fuel : Currently on Liquid Fuel, but Gas Conversion Equipment available.
All relevant
auxiliaries in excellent condition, fully operable, ready for immediate
delivery.
V94.2
heavy-duty Gas Turbines. rated output of 100 MW at ISO conditions.
Each GT unit is
of Single-Shaft, Single
Casing design, equipped with 2 Silo-type Combustion Chambers, a 16-stage Compressor and a 4-stage Turbine.
An air-cooled
Generator, rated at 125 MVA and generating at 10.5 kV is driven from the cold
(Compressor) end of the GT unit.
GT1 & GT2 are currently installed with Siemens diffusion-type Burners for
operation on Distillate-oil Liquid Fuel.
Overview of
Operation & Maintenance
Plant owner has consistently performed maintenance on the GT units in
order to achieve consistently high levels of availability,
generation efficiency, peaking
capability and reliable start-up.
Major Overhauls
have been carried out at intervals of 25.000 EOH.
Inspections on
the GT units are typically performed at 18-month intervals and cover the
following scope:
The owner
performed a Major Overhaul on GT2 in October 1992. Similarly, a Major Overhaul of PPGT1 was last performed in November 1998 with the
following scope:
1. Equipment and
Systems
The following Equipment,
auxiliary and ancillary systems will form part of the Scope of Sale:
Gas Turbine
Unit:
- GT Thermal Block
- GT associated Fire Protection & Detection System / Gas Leak Detection System
- GT Instrumentation & Controls
- GT Monitoring & Protection System
- GT Control Valve Block
- GT Starting Motor and Torque Converter System
- GT DC System with Battery & Charger
- Ignition System
- Fuel Firing System (for Distillate-oil Liquid Fuel)
- Lubrication Oil System and Lubricating Oil-radiator Coolers
- Control Oil System
- On-line Compressor Cleaning System
- Off-line Compressor Cleaning System
- Air Intake & Filter System with Silencers and self-cleaning Elements
- Exhaust Gas Stack, Exhaust Gas Ducting, Silencers, Expansion Joints, Aviation Obstruction Warning Lights and Lightning Arrestors
Generator Unit:
- Generator with air-cooling,
including Generator main Connections, Generator Circuit Breaker, Isolated phase Bus-ducts and auxiliary Switchgear
-
Static Frequency Converter System
- Static Excitation System with automatic Voltage Regulation Control
- Lubricating-oil System and Lubricating Oil-radiator Coolers
- Generator Cooling System
- Generator associated Control, Instrumentation, Metering & Protection System
- Generator Terminal Enclosure
- Internal Piping & Cabling Integral to the Unit
- Neutral Grounding Transformers/Resistors
Transformer
Unit:
- Generator Step-up Transformer (10.5 kV to 66
kV)
- Unit Transformer (10.5 kV to 6
kV)
- Associated Protection, Control & Instrumentation System
Mechanical
Auxiliary & Ancillary
Systems:
- Two (2) Distillate-oil Storage Tanks
- Three (3) Distillate-oil Day Tanks
- Distillate-oil Unloading System (from truck and ship)
- Fire Fighting System, including Diesel Engine and electrically
driven Fire Pumps, Water Storage Tank and Foam Storage Tank
- Fire Detection & Alarm System
- Black-start Diesel Generator and Black-start Air-compressor
- Compressed Air System, including Compressors and Receivers
- Turbine Hall Overhead Cranes
Electrical
Auxiliary & Ancillary
Systems:
- Two (2) Station Transformers (22 kV to 6 kV)
- Two (2) auxiliary Transformers (6 kV to 3.3 kV)
- Two (2) Frequency Converter Transformers (6 kV to 1400 V)
- Two (2) Exciter Transformers (6 kV to 500 V)
- Two (2) Low Voltage Transformers (6 kV to 380 V)
-
One (1) Off-site System Transformer (3.3 kV to 415 V)
- 66 kV Switchgear for Interconnection to Electricity Grid
- 22 kV Switchgear for Station auxiliary Voltage System
- 6 kV Switchgear for Station auxiliary Voltage System
- 3.3 kV Switchgear for Station auxiliary Voltage System
- 380 V Switchgear for Station auxiliary Voltage system
- 380 V Switchgear for Station auxiliary Power System
- 220 V Switchgear for Station auxiliary Power System
- 24 V Switchgear for Station auxiliary Power System
- 220 V DC System including Chargers & Batteries
- 24 V DC System including Chargers & Batteries
- Associated Protection, Control and Instrumentation System
Instrumentation
and Control Auxiliary and Ancillary Systems:
- Siemens Iskamatic Control & Protection System for GT units
- Vibration Monitoring System for GT units
- Ronan Sequential Event
Recording (SER) system
- Electro hydraulic Control System
for GT units
- Station CCTV System
2. Spare Parts and Special Tools
The following Spare Parts and Special Tools will be included in the scope of the asset
sale:
Gas Turbine
Unit Spare Parts
-
Sixty-four (64) pieces of
V94.2 dual fuel diffusion burners (used condition)
Generator Unit Spare Parts
-
18 pieces - SHIM V40 A00A34K42 0704/00100
- 3 pieces - DUPLEX
RES.TEMP.DET ID-NRA00B07E17
- 15 pieces - BRUSH CARBON
NKF634 A00A35B70 0705/1
- 6 pieces - HOLDER DOUBLE
BRUSH ID-NR A00D36C89
- 1 piece - MODULE ME2-2,
MEAS INPUT C71451-A31-A11
- 1 piece - TRANSDUCER ZV4-2,
IMPEDANCE C71451-A61A11
- 1 piece - PASS TP3-1, LOW
C71451-A39-A8
- 1 piece - INDICATOR,
SLIPPING LIMIT C71451-A69-A31
- 1 piece - STABILIZER STU2-2
C71451-A35-A13
- 1 piece - INVERTER WR4/GR3-5
C71451-A37-A22
- 1 piece - SETTER UG4-1,
VOLTAGE C71451-A27-A21
- 1 piece - CONTROL WG4-1,
ANGLE C72451-A95-A4
- 1 piece - INDICATOR N16-2,
ZERO C72451-101-A14
- 1 piece - SET KUS4-1, RELAY
C71451-A65-A10
- 1 piece - SETTER KG12-3,
COMMAND C72451-A107-A9
- 1 piece - CONTROLLER UA1-1,
VOLTAGE C72451-A139-A3
- 1 piece - SET RK2-1, RELAY
CHT11 C72451-A103-A2
- 1 piece - REGULATOR,
VOLTAGE FA-1 C72451-A141-A2
- 1 piece - MODULE POWER
SUPPLY Y3 ARB11-P4D 2523-2A
- 1 piece - MODULE
INTERLOCKING V30 ARB11-P2D 2565-2A
- 1 piece - MODULE TIME Z24
ARB11-P2D 2577-1A
- 1 piece - MODULE, RELAY
Y24-2 ARB-P2D-2573-1A
- 1 piece - MODULE DECOUPLING
V23 ARB11-B2D 2514-1A
- 1 piece - MODULE COMMAND
Y29A 1ARB11-P3D 2598-2A
- 1 piece - MODULE COMMAND
Y29B ARB11-P3D 2599-1A
Gas Turbine
Special Tools
- One (1) Generator Skid
- One (1) Generator Trolley
- One (1) set Generator Rotor Support (consisting of two
pieces)
- One (1) GT Turbine Lifting Beam
- One (1) GT Turbine Bearing Shaft Support
- One (1) set GT Compressor casing
transportation I-beam (consisting of two pieces)
- One (1) GT Compressor Bearing Shaft Support
- Three (3) GT Combustion Chamber Supports
- Three (3) Up-ending Clamps
3. Documentation
Price
16.5 Million USD
For
more information ask by Email
10.) 2 (two) Sets 56 MW each
Originally Dual fuel, liquid side removed but available NEW 1985
NOTE: STEAM TURBINE FAILED AND
THE PLANT BECAME INEFFICIENT.
2 -56,000 KW 80% PF 70,000 KVA BBC GENERATORS, 3 PHASE, 60 CYCLE,
13,800 VOLTS, 3600 RPM, DIRECT CONNECTED TO 2 - 56,000 KW BBC GAS TURBINES , NATURAL GAS FIRED,
( liquid fuel items available site ) TYPE 8, 3600 RPM. NEW 1985.
Each unit is equipped with 400,400#/HR heat recovery steam generator available at
additional cost.
Please note that these units located in the United States were operated
at 60 cycle - 13,800 volts
Gas Turbine
Manufacturer BBC
Type 8
Type 8
Axial Reaction
Number of Compressor Stages 12
Number of Shafts 1
Common
Number of Turbine Stages 3
Speed of Shaft 6339/6349
Mechanical Limit 56
MW
Exhaust Mass Flow 177
kg/s
Exhaust Gas Temp 525C
Casing Design Horizontal
Split
Rotor Design welded
Number of Journel Bearings 2
Number of Thrust Bearings 1
Combustion Chamber
Manufacturer BBC
Tile Temp 820C
Pressure Drop 3,7%
External Diameter 1.95Meters
Reduction Gear
Manufacturer MAAG
Type G-72
S
Generator
Manufacturer BBC
Type WY 16 L0068 LLT
Frequency 50/60
Nominal Output 68.75/82.5
MVA
Rated Voltage 11.5/13.8
kV
Voltage range +/-
5%
Rated Current 3452/3600
A
Speed 3000
rpm
Short Circuit ratio 0.456
kc
Exciter
Manufacturer BBC
Type WBF
6-4 K
Frequency 50/60
Hz
1. Last overhaul, GT-901 - March 2000, GT-902 - November 2000.
2. GT-901 Overhaul March
2000:
Replaced all hot gas path parts
Replaced hot gas casing
Cleaned and inspected compressor
blades, reshimmed rows 10, 11, & 12
Repaired tile carrier to specifications
Replaced 13 row A tiles, 4 row B tiles, 0
row C
Removed liquid fuel oil system
Rebuilt all 3 blow-off valves
Completed alignment inspection, did not
move
Inspected gearbox, combustor inner liner
insert (CILI), rotor, bearings, and generator
I&E calibrated/checked all alarms and
trips, modified control system for the fuel oil system
removal, pressure tested the gas system, calibrated gas control valve, rotor
end face and compressor
discharge temperature transmitter, and the turbine inlet temperature
controller.
GT-902 Overhaul November 2000
Replaced
all hot gas path parts
Replaced tile carrier with spare from
Shell unit
Cleaned and inspected compressor blades
Replaced 33 row A tiles, 39 row B tiles,
43 row C tiles
Removed liquid fuel oil system
Completed alignment inspection, moved
gearbox, generator
Inspected gearbox, hot gas casing,
combustor inner liner insert (CILI), rotor, bearings, and generator
Rebuilt all 3 blow-off valves
I&E calibrated/checked all alarms and
trips, modified control system for the fuel oil system removal, pressure tested
the gas system, calibrated gas control valve, rotor end face and compressor
discharge temperature transmitter, and the turbine inlet temperature controller
3. Operating hours since last OH:
GT-91 -
26,275 OH, 29,395 EOH,
GT-92 -
23,475 OH, 26,375 EOH
Equipment may be in need of an overhaul.
BUT RUNNING WHEN SHUT DOWN
Please note
that these units located in the USA were operated at 60 cycle - 13,800 volts
Both Plants
must be purchased , a Heat
recovery is also available with each Turbine.
Note: The
heat rate on these turbines are as good as the newer high temp Turbines.
These were
originally 50 hz, with reduction gear modification for 60 hz, could go back.
Price is 5.25
Million USD each
HRSG is
needed @ $400,000 each
Gear
modification to 50 hz expected @ $450,000 For more information ask by Email
SCOPE
and PICTURES on request
10.) Two each
Westighouse model W-251b 4
Two each
Westighouse model W 251 b2-6 30.9
mw each' 13.8 kv
complete cooling thru electrical metering and
Circuit breaker.
liquid fired.
These are perfect work horses for operating on
good # 6 oil ( good oil analyse must be
provided )
Westinghouse W 251 b2-6
that unit initiate services on March 14 of
1974, becomes out of service on June 2003, being on the condition of a
available for emergencies.
Turbine hours since chnageout 8,600 &
13,000
Current Facts:
Hours Working: 254.2
Net Production: 5.428.9 Mwh
Consumtiion of LFO 15.457.14 Bts
Disponibility: 97.5 %
Net Effeciency: 22.2 %
Hour Rate: 15.341 Btw/Kwh
Total Hours: 75.539
Starts (successfully) 5.472
Overhaul: 6
CHARACTERISTICS
Turbo-Compressor
Manufacturer-Westinghouse
Open Cycle
Model-W 251 b2-6
Serial No.
17A2106 (SPM)
17A2108 (BARAHONA)
Base Charge
28.300 MW-H
Peak Charge
30.590 MW-H
Reserve 31.400 MW-H
Liquid Fuel Fuel Oil destillated No 2
Speed 4894 RPM
Axiar Compressor Relation 10/1
Axiar Compressor Stages 18
Turbine Stages 3
Frequency (Hz) 60
Reunion 4894/3600
Cross fired tubes 8
Rotor Weight 33,200 Lbs.
Total package Weight 220,000 Lbs.
Rotor Length 27 Ft.
Total Rotor Package Length 44 Ft.
Price 3.85 Million USD each, plus any removal and
freight charges
For
more information ask by Email
11.) 4 each GE
Frame 5-la Gas Turbines,
less than 1,000
hours since last major overhaul
TURBINE DATA
BRAND GE
MODEL MS5001 LA
CAPACITY 16.5
MW
RPM 5100
CONTROLS WDPF
MHZ FLOATING POINT CENTRAL
PROCESSOR
ELECTRICAL FULL UTILITY ELECTRICAL, WITH
METERING, RELAYS ETC.
SYNCH EQUIPMENT FACTORY, AUTOMATIC :: AUTO
SYNCHRONIZER
EXHAUST SYSTEM FACTORY COMPLETE
RPM 5100
STAGES: 15
EXHAUST GAS FLOW 255.5 LB/SEC
AIR INTAKE INCLUDED
HUMIDITY 83%
TEMP 28
c
AREA FOR TURBINE 565 METERS
TEMP 964
f
AIR @ COMPRESSOR 86 f
NO. OF COMBUSTION 10
COOLING FIN / FAN
GENERATOR
GENERATOR GE
MODEL
ATB
INSULATION CLASS F
COOLED AIR
PF 0.8
CAPACITY 20780
KVA
CYCLE 60 HZ
VOLTAGE 13.8KV
AMPS 788
AMPS
EXCITER RPM 3600
POLES 2 POLES
AUXILIARY POWER FROM STATION TRANSFORMER , WITHIN UNIT
STARTING BLACK START DIESEL ( one per group )
WEIGHTS : GENERATOR :::: 147,800 LB’S
TURBINE :::: 176,000 LB’S
Price 3.45 Million USD each
SCOPE and PICTURES on request
For more information ask by Email
12.) Two each
10.25 mw Turbine sets
LMA
1500 Turbine Module
The
turbine skid assembly is contained in a weather-resistant sound reducing enclosure
containing the fully assembled LMA 1500 engine and power turbine. Skid
installation includes wiring, instrumentation and piping. The skid is provided
with a gas and fire detection/suppression system. An exhauster fan mounted on
the skid roof window draws clean filtered air through the enclosure. The
enclosure air enters through a window on each side of the skid. Windows are
fitted with filters, rain hoods, and fire dampers that are actuated by the fire
suppression system.
The module is completely assembled
and ready to operate including lube oil, hydraulic oil and fuel piping,
instrumentation, and pre-wired electrical components. The module foundation is
provided by customer. seller will supply
foundation drawings.
Section 1 - Equipment
OVERVIEW
The equipment is outlined in
the accompanying equipment list (Section 2) and summarized below. The unit
subassemblies are modularized for quick installation and come fully assembled
and ready for operation.
Turbine Module
The turbine skid assembly is
contained in a weather-resistant sound reducing enclosure containing the fully
assembled LMA 1500 engine and power turbine. Skid installation includes wiring,
instrumentation and piping. The skid is provided with a gas and fire
detection/suppression system. An exhauster fan mounted on the skid roof window
draws clean filtered air through the enclosure. The enclosure air enters
through a window on each side of the skid. Windows are fitted with filters,
rain hoods, and fire dampers that are actuated by the fire suppression system.
Turbine Air Intake and Exhaust
The turbine air intake
system consists of a filter house, silencer and air intake plenum. Rain hoods
are fitted over the filter elements. The turbine exhaust system includes a
transition piece, plenum, silencer and stack.
Generator Module
The weather resistant, sound
reducing skid enclosure contains the fully assembled Lufkin speed reduction
gear and the Ideal Electric 13..8 kV generator with incoming line cubical. The
skid is provided with a fire detection/suppression system. Outside air is drawn
through the generator via three skid enclosure windows. Windows are fitted with
filters, rain hoods, and fire damper’s actuated by the fire suppression system.
The air is vented from the generator to atmosphere via the skid roof window and
stack.
Controls
An integrated GE
Global/Woodward control system allows fully automated operation with operator
interface at a 15 screen HML The HMI would be located in customer's designated
area. As well as controlling the turbine I generator operation, the system
provides normal startup and shutdown sequencing, and start-up permissive!. The
equipment is monitored for generator output voltage, frequency and other key
generator electrical parameters, vibration level, operating speeds, bearing and
lube oil temperatures, fuel and lube oil flow and lube oil reservoir levels.
Out of limit operational parameters trigger an alarm at the HMI. If critical
out of limit parameters are not corrected, the control system will cause either
a normal shutdown, or in more critical situations, an emergency shutdown.
Lube Oil I Hydraulic Engine Starter Modules.
There are two lube oil skids
each with separate oil systems and reservoirs as follows:
The High Temperature Turbine Oil Skid
The skid has a separate
reservoir for the synthetic oil with one pump supplying the turbine bearings
and one pump scavenging the turbine return oil header. The oil is also pumped
to the
inlet guide vane actuators
and is cooled by circulation through an air-cooled exchanger. .
The Conventional Lube Oil
Skid
Lube/hydraulic oil is
contained in a separate reservoir with pumps for lubricating the gearbox and
generator bearings. The oil is also pumped to the hydraulically operated engine
starter. Two air coolers in parallel are used to provide lube oil cooling.
Electrical Equipment
The generator is protected
against electric faults by a GE Multi Un protection relay.
The control system and the
voltage regulator are installed in NEMA cabinets for installation in
Customer’s motor control
center or other customer designated area.
A power distribution panel
is included for the lubrication skid motors as well as other support functions.
The power distribution panel provides isolating disconnects and starters for
the motor circuits on the auxiliary skids.
The electrical equipment
includes a 1000A isolation breaker with monitoring meters for voltage and
current, as well as a digital synchronizer and neutral ground-fault resistor
assembly
Turbine Fuel System
The system is designed to
bum natural gas at 275 psig. There are also components that will allow
switching to #2 diesel oil as an alternate fuel source. Required diesel oil
pressure is 650 psig.
Inlet Air Fogger System
Each turbine has an Amco
inlet air fogging system that provides evaporative cooling to the inlet air.
The fogger is designed to add the exact amount of moisture required to saturate
the inlet air, thus reducing the air temperature to close to the dew point.
Customer is required to supply softened water to the high-pressure fogging
water pumps which are mounted on a separate fully assembled fogging skid.
Fogging nozzles are .located in the turbine inlet air filter house.
Section 2 - Equipment Scope
of Supply
The following is a
description of the key equipment provided with the turbine I generator.
I) LMA 1500 Turbine Module
The module is completely
assembled and ready to operate including lube oil, hydraulic oil and fuel
piping, instrumentation, and pre-wired electrical components. The module
foundation is
provided by customer.
seller will supply foundation drawings.
Engine
a) Bellsouth and bullet nose
air intake with FOD screen
b) 17 stage turbine air
compressor. The inlet guide vanes and the first 6 stages of stator vanes are
variable in pitch to provide optimum performance over the entire operating
range. Maximum speed is 7650 RPM.
c) a through-flow cannular
designed combustion system utilizing 10 simple. Orifice type fuel nozzles with
liners
d) a 3-stage turbine driving
the turbine air compressor and feeding the power turbine.
Turbine outlet temperature
(EGT) maximums are:
1) "base
load" 1035 f
2) "peak
load" 1115 f
3) "peak reserve"
1175 F
e) The EGT and the air
intake temperature, are used to control the engine inlet guide vane setting.
Power Turbine
Hot gas from the engine
turbine is fed t9 a GE single stage power turbine which runs at a constant
speed of 5500 RPM. Power turbine speed is controlled by the Woodward governor
regulating fuel flow.
Turbine Skid (L 21', W 10'
8") Containing the Engine and Power Turbine
a) The turbine skid enclosure provides weather protection and
is sound proofed (85 d8a at 3
b) The skid enclosure has two air intake windows fitted with
filters, rain hoods, and fire
dampers, an air exhaust roof window with fire dampers,
and two equipment doors.
c) The skid fire protection
system includes:
1) smoke J fire detection
module
2) gas detector module
3) logic module that closes
the skid air intake and exhaust louvers and actuates a CO2 cylinder
d) The enclosure air exhaust
system includes:
1) exhaust fan
2) silencer
3) stack with rain hood
Turbine Instrumentation
a) (2) gas turbine speed
sensors (magnetic pickup type)
b) (2) power turbine speed
sensors (magnetic pickup type)
c) (12) power turbine inlet
temperature probes with type k thermocouples d) (2) accelerometer type turbine
air compressor bearing vibration sensors e) (3) accelerometer type power
turbine bearing vibration sensors
f) RTD type lube oil supply
temperature sensor
g) (5) RTD type oil scavenge
sump temperature sensors
h) RTD type turbine air
inlet temperature sensor
i) lube oil supply pressure
sensor
j) scavenge oil pressure
sensor
k) compressor discharge
pressure sensor
I) fuel gas pressure sensor
m) fuel oil pressure sensor
(if required)
n) power turbine inlet
pressure sensor
0) (2) IGV actuator position
sensors
p) fuel valve position
sensor
q) fuel flow measuring
device
II) Turbine Inlet Air and Exhaust System
These systems are field assembled
after the turbine. is set on its foundation. Systems require foundations
provided by customer. Seller will supply foundation drawings.
The footprint for the inlet
air duct, turbine skid, exhaust air duct and generator skid is approximately 55' x 11'.
Air Intake Filter house
a) Rain hoods
b) Trash screen
c) Seventy two 2'x2' inlet
air filters with rain hoods
d) Filter.1.P transmitter
e) Service lighting
Air Intake Silencer
Silencer is designed for an
external sound level of 85 dBa at 3 ft.
Air Plenum
a) Double doors
b) Floor drain
c) Service lighting
Turbine Exhaust
Includes:
a) Transition piece, exhaust plenum and
expansion joint
b) Silencer designed for an external sound
level of 85 dBa at 3 ft.
c) stack
LMA 1500 Generator Module
The module is completely
assembled and ready to operate including lube oil, instrumentation, and
pre-wired electrical components including the incoming line cubical. Module
foundation is provided by customer.
Gear Box ,
The Lufkin parallel
horizontal offset speed reducer is designed for input speed of 5500 rpm and
output speed of 1800 rpm, and rated for 15,000 hp with a 1.4 AGMA SF.
Couplings
The couplings between the
power turbine and the gear box and also between the gear box and the generator
are torque tube type, Kop-Flex.
Generator
The Ideal Electric
horizontal brush less air-cooled AC generator is rated for 13.8kV @ 60 Hz (1800
rpm); and is supplied with an integral lube system.
Generator Skid (L 23; 0'\ W
10' 11", H 8'2") Containing the Gearbox and Generator
Includes:
a) weather protected
enclosure with sound proofing to 85 dBa at 3 ft.
b) three air intake windows
fitted with filters, rain hoods, and fire dampers. Enclosure air is drawn
through the generator. The air is then ducted from the generator to a roof
window fitted with fire dampers.
c) two equipment doors.
d) fire protection system
including:
smoke I fire detection module
logic module that closes the skid air
intake and exhaust fire dampers and actuates a CO2
cylinder'
e) Enclosure air exhaust
stack with rain hood.
f) NEMA cabinet containing
the incoming power line connection terminals. Cabinet is
mounted on the outside of the skid. ' .
Gearbox and Generator Instrumentation
a) GE Multi Un SR 489
generator protection system including: 1) power, frequency, voltage current and
phase monitors 2) ground fault detection systems
3) key generator temperature
monitoring
4) circuit breaker failure
5) voltage and current
transformer supervision
b) Sensors that measure:
1) generator stator phase A,
B, C temperatures
2) generator bearing
temperatures
3) generator vibration
4) gearbox and generator
bearing temperatures
5) gearbox bearing lube oil
temperature and pressure 6) gearbox high and low speeds (magnetic pickup type)
IV) Lube oil Hydraulic
and Engine Starter Skids
The modules are completely
assembled and ready to operate including all oil tubing and hoses,
instrumentation including pressure relief valves, and pre-wired electrical
components. Duplex filters are installed downstream of the oil pumps Equipment
and piping are stainless steel. Equipment is contained within the approximate
footprint of L 20', W 8'
There are two oil modules
each with separate. Reservoirs as follows:
Turbine High Temperature
Synthetic Lube Oil Skid
This system supplies the
high temperature synthetic oil to the turbine bearings and to the IGV
actuators.
Includes:
a) a stainless steel reservoir
b) One Thermal Transfer air cooled oil heat
exchanger
c) Lube oil pumps with motors supplying/scavenging
the bearings and also the oil cooler
d) a pump supplying lube oil to the IGV actuators
Conventional Lube/Hydraulic
Oil Skid
This system supplies the
lube oil to the gearbox and generator bearings, and the hydraulic oil to
the turbine starter. .
Includes:
a) An 800 gal stainless
reservoir
b) Two Thermal Transfer air
cooled oil heat exchangers operated in parallel
c) Lube pumps with motors
supplying the gearbox (SInd the generator
d) Hydraulic oil pump with
motor supplying the turbil1_ starter
e) Hydraulic turbine starter system
Instrumentation
Instrumentation on the
discharge side at _ach .of the oil pump includes:
a) Duplex filter (containing
5 micron cartridge_) with delta P sensor
and high AP switch b) oil pressure and temperature sensors.
c) Pressure relief valve
discharging back to the reservoir.
V) Turbine I Generator
Control System
GE Global/ Woodward Atlas PC
Digital Control includes:
a) Power turbine and
generator speed controls with a. Woodward governor that sets the fuel
flow
b) Inlet guide vane (IGV) position controls. The IGV sets
the engine speed. The primary IGV
control input is the turbine inlet air temperature. The
control has various overrides, of which
high engine exhaust temperature is one of the most
significant.
c) Gas compressor fuel vent
valve controls (vent valve opens in response to most shutdown
Initiators) .
d) Generator controls using
a Woodward DSLC (digital synchronizer and load control)
e) CONTROL EQUIPMENT FOR:
1) Monitoring all instrument read outs and initiating an
alarm when out of allowable' range
2) Monitoring the critical operating parameters and
initiating a normal shutdown when out of allowable range
3) Monitoring the most critical operating parameters and
initiating an emergency
shutdown when out of allowable range
4) indicating the status of
the start up permissive that have to be met before a start up can commence
indicating the status of
each item in the start up sequence list
indicating the status of
each item on the shut down sequence list
providing inputs to and
outputs from the15 screen HMI that is installed in the
customer designated building .
Electrical
A) NEMA cubicle (approximate
dimensions 95"Lx 37'W x 100"H) containing:
1) 15KV 1200A main breaker
2) GE Model 489 Multi Un
generator management relay
3) current and voltage
transformers
4) voltmeters
5) Yokogawa synchro scope
and Basler Electric sync-check relay
6) indicating lights
7) switches
B) A NEMA cubicle (approximate dimensions
33"L x 34'W X 92"H) containing:
1) the Basler Electric SSR
series voltage regulator
2) auto-synchronizer relays
3) VAR/power factor
controller
C) The neutral grounding
resistor
MCC NEMA cubicle
(approximate dimensions 80"L x 30'W x 90"H) containing:
1) Starters for all the
motors on the lube oil and turbine oil starter skids
2) Turbine enclosure exhaust
fan. Starter
3) Circuit breaker lifting device
AMCO Fogging Module TO BE
ADDED TO COMPENSATE FOR HIGH AMBIENT
TEMP
a) a pump skid (approximate
dimensions TL x 5'W) containing:
1) Fogging pump with motor
2) Motorized ball valves
controlling zone flow
3) Service disconnect,
breaker, motor starter with overload 4) PLC with operating and safety logic
fogging manifold and nozzle array mounted
in air intake filter house interconnecting ss tubing
instruments and controls mounted on skid
including:
1) Pressure transmitters on water supply and
pump discharge
2) Temperature transmitter on pump discharge
3) Solenoid valve on pump suction
4) Weather station
|
|
Description =-> |
|
WEIGHT. |
|
GENERATOR |
GENERATOR. GEAR BOX.
SKID FRAME. |
85,000 LBS |
|
|
SKID |
ENCLOSURE &: ROOF.
EXAUSTER FAN . |
||
|
TURBINE: |
TURBINE. POWER turbine
EXAUST - |
|
|
|
SKID |
Plenum. SKID FRAME.
ENCLOSURE |
25,000 LBS |
|
|
|
FAN &: FAN SIL£NCER |
: |
|
|
INLET AIR |
INLET AIR PLENUM &
SUPPORT' |
TBA |
|
|
PLENUM |
|
|
|
|
FILTER |
AIR INLET HOUSE.,
Filter SETS, |
TBA |
|
|
HOUSING |
JOINT SILENCER.
PLATFORM &: SUPPORT |
TBA |
|
|
|
STRUCTURE. |
|
|
|
EXHAUST |
EXHAUST -STACK.
SILENCER & SUPPORT |
TBA |
|
|
STACI< |
STRUCTURES |
|
|
Price 2.35 Million USD each
For
more information ask by Email
13.) 42 MW 108 bar/
520°C/ 150 t/h Back Pressure Turbine
including Boiler BBC 1974
STEAM TURBINE
Back pressure turbine with a high-middle and
low-pressure part. It was operated




without any breakdowns.
The blades of the low-pressure part will be renewed for
achieving the whole electrical power output of
42 MW.
Technical specification:
Manufacturer BBC, Baden, CH
Year of Construction 1974
Operating Mode Back pressure
Power Output 42 MW
Steam-
Mass flow 150 tons per hour
Live Steam Temperature 520 °C
Live Steam Pressure 108 bar
Rotation Speed 3000 rpm
Without isolation, dismantled and renewed with
new blades
ELECTRICAL GENERATOR
The generator also may be considered almost as
good as new. It was able to operate
without any breakdowns.
Technical Specifications:
Manufacturer BBC, Baden, CH
Year of Construction 1974
Power Output 42 MW
Voltage 13.8 kV
Rotation Speed 3000 rpm
Cooling
Air Cooling 108’000 m3/h
Dismantled and ready for transport
STEAM GENERATOR
This high pressure steam boiler can be fired with
light oil or natural gas and satisfies
the environment standards without any
problems. All boiler parts are asbestos-free.
The steam generator may be considered almost
as good as new.
Technical Specifications:
Manufacturer Wehrle Werke, Emmendingen, D
Year of Construction 1974
Number of Burners 6
Fuel light oil, natural gas
Steam-
Production Quantity 150 tons/hour
Output temperature 525 °C
Output pressure 110 bar
Exhaust air Satisfies the emission limits of
Switzerland
Without isolation and dismantled
TRANSFORMER
Moser Glaser Transformer “unused” Type
T30W 12/5000 build in 1994.
Technical data:
Manufacturer Moser Glaser, CH
Year of Construction 1994
Type of Transformer T30W 12/5000
Power of Transformer 11/6 kV, 20 MW
Condition of Transformer Unused
Dismantled and ready for transport
CONTROL PANEL
Control Desk with Siemens (Mosaic-Desk) with
Synoptic, including 20 electrical
cabinets.
Technical data:
Manufacturer BBC, Baden CH and Siemens
Renewed in 1994
Number of electrical cabinets 20
Number of control desk 1
Dismantled and ready for transport
Availability: Immediately
Price: 8,300,000.-. EUR
For
more information ask by Email
14.)
100 MW Power Barge
with Pratt & Whitney FT4C-1D gas
turbines on diesel or natural gas
The FT4C-1D Twin Pac is an outdoor, completely
self-contained, automatic, gas turbine powered electric generating plant, nominally
50 HZ rated at 51 MW at 15* C. The unit contains all the equipment required for
local unattended operation and provisions for interconnection to a remote
control panel.
Price is 45 Million USD
For more information ask by Email
15.) 92 MW Power Barge
with GE Frame 6B gas turbines
on diesel
Price 51 Million USD
with HFO option for an additional 5
Million USD
For more information ask by Email
16.) 63
MW Diesel Electric Power Plant Equipment
consisting of
48 MW Diesel Electric Power Plant Equipment
Six (6) units of 8 MW, AC Electric Generator
Set
Diesel Engine
Make
Fuji, SEMT-Pielstick
Model
18PC2-5V
YOM
1974
Number
of Cylinder 18
Power
11,700 Hp
Speed
514 rpm
Turbo
charged
Mounted
on massive concrete foundation
Engine
No. 1, 2, 3, 4, 5, 6
Alternator
Make
Fuji Electric Co., Ltd.
Type
F525/34-14
YOM
1974
Power
Rating 10,000 kVA (8000 kW)
Current
875 amps.
Voltage
6600 volts
Phase
3-phase continuous rating
Power
Factor 0.80
|
Equipment |
Q’ty |
Description
|
|
Smoke Stack
|
1 |
Mild steel plate of welded construction, 4 m
diameter at bottom to 3 m diameter at top, 13 mm thick at bottom reducing to 6
mm thick at top, 300 meters overall height, with 3 landings and ladder |
|
Black Start
Generator |
1 |
Caterpillar, Model 3405, 1997 year mfd., 500
kva/400 kW rating, 240 volts, 3-phase, powered by 6-Cylinder Diesel engine,
turbo charged, skid mounted |
|
Ultrasonic
Cleaning Machine |
1 |
Vibraclean, Model VC7200/1300 |
|
CIP Module
|
1 |
Lutz/02030-018654, Type B2230, 8,5 li/min
pump flow rate |
|
Sealing Water
Pumps |
2 |
DP Pump, Type DPVF 2-130, 0,8 li/sec capacity,
each driven by 2,2 kW electric motor |
|
Soft Water
Pressuring Tank |
1 |
Mild steel plate of welded construction,
Model V8, 790 gallons capacity, approximately 1219 mm diameter x 2591 mm
high, 150 psig pressure |
|
Deaerating
Tanks |
6 |
Mild steel plate of welded construction, 40
liters capacity |
|
Graviner Oil
Mist Detectors |
6 |
|
|
CMR Bearing Temperature Monitor Panels |
6 |
|
|
Lubricating Oil Sump Tanks |
6 |
Mild steel plate of welded construction, 2,40
m x 2,40 m x 1,80 m H, 13,500 liters capacity
|
|
Main Lube Oil Lubricating Pumps |
6 |
Japan, rotary gear type, 150 mm suction and
discharge diameter, each driven by 74,6 kW Electric Motor (3-phase, 440
volts, complete with motor controller and other standard accessories) |
|
Air
Compressors |
5 |
Ingersoll Rand, 3- cylinder reciprocating
piston type, each belt driven by 15 kW electric motor |
|
Air Receiver
Tanks |
2 |
Mild steel plate of welded construction, cylindrical,
750 mm diameter x 2400 mm high |
|
Oil Drip
Tank |
1 |
Mild steel plate of welded construction,
cylindrical, 1,50 m diameter x 3,0 m length, equipped with Oil Pump (Rotary
gear type, 50 mm suction and discharge diameter), driven by 3,73 kW Electric
Motor (3- phase, 230 volts) |
|
Deepwell
Pump |
1 |
Grundfos, submersible multi-stage
centrifugal type, driven by 55,95 kw electric motor, black iron pipe casing,
350 mm diameter, 150 mm diameter drop and discharge pipe, 300 meters deep,
complete with controls and other standard accessories |
|
Cooling
Towers |
6 |
Intercool, FRP construction, cylindrical
type, 7,26 meters diameter x 8,81 meters high, 2248 cu meter /hr water
volume, with blower, driven by 14,92 kW Electric Motor complete with standard
accessories |
|
Concrete
Basin |
1 |
Reinforced concrete construction, 30 m L x
20 m W x 2,40 m H, open top |
|
Switchboard |
1 |
RG Trans-Electric Corp., metal enclosed, 2 vertical
sections with 1200 A main breaker and 6 magnetic controllers for cooling
fans |
|
Raw Water
Tank |
1 |
Mild steel plate of welded construction, 6,0
m diameter x 7,20 m high, 189,000 liters capacity, vertical cylindrical tank with
ladder and top port and other standard accessories |
|
Soft Water
Pumps |
2 |
Aurora, single stage centrifugal type, 100
mm x 75 mm suction and discharge diameter, driven by 3,73 kW Electric Motor
(3- phase, 220 volts, 1730 rpm, complete with controls and other standard
accessories) |
|
Brine Tank |
1 |
Plastic construction, 900 mm diameter x 1200
mm high with cover |
|
Water
Softeners |
2 |
Mild steel plate of welded construction, 1,20
m diameter x 1,80 m high, vertical cylindrical tank with resins, 4- leg
support, complete with standard accessories
|
|
Treated Water
Tank |
1 |
Mild steel plate of welded construction,
1,80 m diameter x 4,80 m high, vertical cylindrical tank, 4- leg support,
complete with standard accessories |
|
Cooling Water Circulating Pumps |
4 |
Weinmann, single-stage horizontal split-case
centrifugal type, 300 mm x 250 mm suction and discharge diameter, each driven
by 93,25 kW Electric Motor (3- phase, 230/460 volts, 1775 rpm) |
|
Bunker Oil Storage Tanks |
2 |
Mild steel plate of welded construction,
12,20 m diameter x 13,50 m high, 1,300,000 liters capacity, vertical
cylindrical tank, mounted on concrete foundation, complete with spiral
stairs, volume indicator, manhole and other standard accessories |
|
Filter
|
1 |
Toyo Filter, 150 psi, flange bolted |
|
Diesel Storage Tank |
1 |
Mild steel plate of welded construction, 4,84
m diameter x 6,50 m high, 100,000 liters capacity, vertical cylindrical tank,
complete with standard accessories |
|
Lube Oil Storage Tanks |
1 |
Mild steel plate of welded construction,
3,86 m diameter x 4,55 m high, 50,000 liters capacity, vertical cylindrical
tank, complete with standard accessories
|
|
Oil Pumps
|
2 |
Daito Kogyo, Japan, Type KHR-10-40, rotary
gear type, 50 mm suction and discharge diameter, driven by 1,50 kW Electric
Motor (3-phase, 230 volts) |
|
Oil Pump
|
1 |
Daito Kogyo, Japan, Type KSR-25-90, rotary gear type, 75 mm
suction and duischarge diameter, driven by 5,50 kW Electric Motor (3-phase,
220 volts) |
|
Oil Heaters
|
2 |
Mild steel plate of welded construction,
shell and tube type, with aluminum claddings, 450 mm diameter x 1500 mm
length |
|
Oil Pump
|
1 |
Daito Kogyo, Japan, Type KSR-10-4, rotary
gear type, 50 mm suction and discharge diameter, driven by 1,5 kW Electric
Motor (3-phase, 220 volts, complete with control and other standard
accessories) |
|
Oil Transfer Pump |
1 |
Daito Kogyo, Co., Ltd., rotary gear type,
Type KSR-25-120, 75 mm suction and discharge diameter, driven by 7,46 kW
Electric Motor (3-phase, 220 volts, 1750 rpm, complete with control and other
standard accessories) |
|
Fuel Oil Purifiers |
2 |
Mitsubishi Chemical Machinery Mgf. Co. Ltd.
Self-Jector, Type SJ8000, 8000 liter/hr capacity, 5000 rpm, driven by 15 kW
Electric Motor (3-phase, 230/460 volts)
|
|
Fuel Oil Purifiers |
3 |
Mitsubishi Chemical Machinery Mgf. Co. Ltd.
Self-Jector, Type SJ6000, 6000 liter/hr capacity, 5500 rpm, driven by 11 kW
Electric Motor (3-phase, 230/460 volts)
|
|
Oil Separator Tank |
1 |
Reinforced concrete construction, 9,0 m L x 2,40
m W x 2,0 m depth, 3 compartments, with stairs |
|
Oil Sump Pit
|
1 |
Reinforced concrete construction, 1,20 m x
1,20 m x 2 m depth, equipped with 2- Oil Transfer Pumps, Rotary gear type, 50
mm suction and discharge diameter, driven by 1,5 kW Electric Motor (3-phase,
230 volts, complete with standard accessories) |
|
Sludge Tanks
|
2 |
Mild steel plate of welded construction, 2,0
m diameter x 6,0 meters length, cylindrical horizontal tank, with steel
support |
|
Diesel Service Tank |
1 |
Mild steel plate of welded construction,
2,40 m diameter x 3,0 meters high, vertical cylindrical tank, complete with
standard accessories |
|
Bunker Settling Tanks |
2 |
Mild steel plate of welded construction, 2,40
m diameter x 3,0 meters high, vertical cylindrical tank, complete with
standard accessories |
|
Bunker Service Tanks |
2 |
Mild steel plate of welded construction,
2,40 m diameter x 3,0 m high, vertical cylindrical tank with aluminum
claddings and rockwool insulation, electrically and steam heated with 20 kW
electric heater, complete with standard accessories |
|
Bunker Oil Transfer Pumps |
2 |